4.1.1 HORIZONTAL INSTALLATION

THE FIRESTOP ASSEMBLY MUST BE INSTALLED WITH THE VENT SHIELD TO THE TOP.
TERMINALS MUST NOT BE RECESSED INTO A WALL OR SIDING MORE THAN THE DEPTH OF THE
This application occurs when venting through an exterior wall.
Having determined the correct height for the air terminal
location, cut and frame a hole in the exterior wall as
illustrated to accommodate the fi restop assembly.
Dry fi t the fi restop assembly before proceeding to
ensure the brackets on the rear surface fi t to the
inside surface of the horizontal framing.
The vent shield must be installed to the full depth of
the combustible wall. The length of the vent shield
may be cut shorter for combustible walls that are
less than 8 1/2" (216mm) thick.
reduced side clearances or move the shield for reduced top
clearances.
A. Apply a bead of caulking (not
supplied) around the corner edge of
the inside surface of the fi restop
assembly, fi t the fi restop assembly
to the hole and secure using the
4 screws (supplied in your manual
baggie).
NOTE : Do not fi ll the air space
between the fi restop spacer and the exterior wall with any type of insulating material (i.e., spray foam).
B. Once the vent pipe is installed in
its fi nal position, apply red
fi restop.

4.1.2 VERTICAL INSTALLATION

This application occurs when venting through a roof. Installation kits for
various roof pitches are available from your authorized dealer / distributor.
See accessories to order specifi c kits required.
A. Determine the air terminal location, cut and frame a square opening as
illustrated in the ceiling and the roof to provide the minimum 1" (25mm)
clearance between the vent pipe and any combustible material. Try to
center the vent pipe location midway between two joists to prevent
having to cut them. Use a plumb bob to line up the center of the
openings. A vent pipe shield will prevent any materials such as
insulation, from fi lling up the 1" (25mm) air space around the pipe.
Nail headers between the joist for extra support.
B. Apply a bead of caulking (not supplied) to the framework or to the
Wolf Steel vent pipe shield plate or equivalent (in the case of a fi nished
ceiling), and secure over the opening in the ceiling. A fi restop must be placed
on the bottom of each framed opening in a roof or ceiling that the venting
system passes through. Apply a bead of caulking all around and place a
fi restop spacer over the vent shield to restrict cold air from being drawn into the
room or around the fi replace. Ensure that both spacer and shield maintain the required
clearance to combustibles. Once the vent pipe is installed in its fi nal position, apply
Mill Pac sealant (W573-0007) (not supplied) or red RTV silicone (W573-0002) (not
supplied) between the pipe and the fi restop assembly.
C. In the attic, slide the vent pipe collar down to cover up the open end of the shield and
tighten. This will prevent any materials, such as insulation, from fi lling up the 1" (25mm)
air space around the pipe.
WARNING
!
RETURN FLANGE OF THE MOUNTING PLATE.
CAULKING
FIRESTOP
NOTE: Bend the tabs for
RTV silicone sealant (W573-0002) (not supplied) between the pipe and the
VENT
SHIELD
SPACER
CAULKING
FINISHING
MATERIAL
20.7D
VENT PIPE
21
DETERMINE
THE
CORRECT
HEIGHT
FIRESTOP
UNDERSIDE OF
JOIST
CAULKING
SHIELD
VENT
PIPE
COLLAR
VENT
PIPE
SHIELD
21.1B
W415-1285 / F / 12.21.16
EN

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Bhd4nBhd4pg

Table of Contents