Commissioning
14.5

Testing the Configuration in Conjunction with the PLC

Test with PLC
Test the OP interaction with the connected PLC. This checks that the correct
connected
data areas have been configured.
14-8
Artisan Technology Group - Quality Instrumentation ... Guaranteed | (888) 88-SOURCE | www.artisantg.com
Step
1
Connect the OP to the PLC.
A message on the OP indicates that it has been connected successfully.
2
Acknowledge this message.
3
Set the OP in ONLINE mode using the System Settings standard screen.
All the items contained in the configuration that are necessary for
communication with the PLC can then be tested. Depending on the
configuration, these might be:
S
event and alarm messages
S
buffers for event messages and alarm messages
S
print functions
S
automatic message logging
S
screen selection etc.
Action
OP27, OP37 Equipment Manual
Release 05/99