STEP 5
NOTE: External plumbing confi guration will vary depending on the location of basin, location of main stack and
available space.
5.1)
Place the pump in the basin as shown in Figure 5.1.
NOTE: If installing the internal trap, rotate the tail pipe to the orientation shown in Figure 5.1.
5.2)
Install the lid components as shown in Figure 5.2.
NOTE: Pull excess cordage through the opening and install the cordseal as shown in Figure 5.3A.
Insure o-ring is in the cap before installation.
5.3)
Place the basin assembly in its fi nal position and complete plumbing. Secure all connections
(shown in 5.3A or 5.3B).
Figure 5.1
KEY
UNION
(PURCHASED SEPARATELY)
INLET
CORD SEAL
GFCI
OUTLET
CAP
INTERNAL TRAP INSTALLATION
STEP 6
6.1)
Plug the cord into a properly grounded GFCI receptacle.
6.2)
Fill tank with water.
6.3)
Check all plumbing for leaks as the basin fi lls.
6.4)
Verify that the pump starts and stops.
6.5.) Check the discharge line for leaks as the pump empties the basin.
6.6.) Repeat steps 6.2 to 6.5 as necessary to insure proper operation.
6.7.) If problems persist refer to the troubleshooting guide located on page 2 of this manual.

Final Assembly

TRAP INLET
O-RING
SK2005
CAP
DISCHARGE PIPE
CHECK VALVE
*
CHECK VALVE MUST BE
PURCHASED SEPARATELY
Figure 5.3A
FOR MODEL 104 & 132-0005.
Initial Testing of Drain Basin System
© Copyright 2005 Zoeller Co. All rights reserved.
2" SLP x NPT
CORD SEAL
SEE NOTE
O-RING
CAP
CAP SECTION VIEW
UNION
(PURCHASED SEPARATELY)
CAP
CORD SEAL
*
INLET
GFCI
OUTLET
7
1 1/2" SLP x NPT
(APPLY SEALANT TO THREADS)
1/4 - 20 x 1"
S.S. SCREWS
1/4 - 20 STD.
S.S. FLAT WASHERS
DISCHARGE PIPE
1/4 - 20 STD.
S.S. FLAT WASHERS
1/4 - 20
S.S. NUTS
(TORQUE TO 30 IN-LB)
Figure 5.2
DISCHARGE PIPE
CHECK VALVE
STANDARD INSTALLATION
Figure 5.3B
SK2007A
*