5 TRIAL OPERATION AND ADJUSTMENT

5. TRIAL OPERATION AND ADJUSTMENT

5.1 Checklist before Trial Operation

Model name
(1) Check that the main base unit is Q38DB or Q312DB.
(2) Check that the model name of module is correct.
(3) Check that the installation order is correct.
(4) Check that the damage for installed modules.
(5) Check that the modules are installed correctly.
Main base unit/
(6) Check for looseness, rattling or distorted installation.
Extension base unit
(7) Check that the module fixing screw tightening torque is as specified.
(8) Check that the total I/O points of I/O modules and intelligent function
modules do not exceed the I/O points of the CPU module.
(1) Check that the model name of power supply modules is correct.
(2) Check that the wire sizes of cables are correct.
(3) Check that the power line is wired correctly.
(4) Check that FG and LG are wired correctly.
(5) Check that the terminal screws are tightened correctly.
Power supply module
(6) Check that the terminal screws are tightening torque is as specified.
(7) Check that the 100VAC, 200VAC and 24VDC wires are twisted as
closely as possible respectively and run in the shortest distance.
(8) Check that the 100VAC, 200VAC and 24VDC wires are not bind the
cable together with and run close to the power wires.
(9) Check that grounding of the earth terminal FG and LG.
(1) Check that the model name of PLC CPU modules is correct.
PLC CPU module
(2) Check that the modules are installed to CPU slot or I/O slot 0 to 2 of
the main base unit.
(1) Check that the Q173HCPU(-T)/Q172HCPU(-T)/Q173CPUN(-T)/
Q173CPUN(-T)/Q173CPU/Q172CPU is not used.
(2) Check that the modules are installed to I/O slot 0 to 2 of the main
base unit.
Q173DCPU/Q172DCPU
Motion CPU module
(3) Check that the module fixing screws are tightened correctly.
(4) Check that the EMI forced stop input is wired correctly.
(5) Check that the external battery is installed.
(6) Check that the battery cables are connected correctly.
(1) Check that the wire size of cable is correct.
(2) Check that the terminal block screws are tightened correctly.
(3) Check that the cables connected to each terminal of terminal block
correspond to the signal names.
(4) Check that the external power supply are connected correctly.
I/O module
(24VDC, 5 VDC)
(5) Check that the 100VAC, 200VAC and 24VDC wires are twisted as
closely as possible respectively and run in the shortest distance.
(6) Check that the 100VAC, 200VAC and 24VDC wires are not bind the
cable together with and run close to the I/O wires.
(7) Check that the I/O wires are wired correctly.
Table 5.1 Checklists before Trial Operation
Confirmation Items
5 - 1
Check
Reference
2.4.3
2.2
2.1.4
4.1.3
4.1.1
4.1.1
Refer to the "Q173DCPU/
Q172DCPU" Motion
controller Programming
Manual(COMMON)"
2.4.2
4.4.1
4.4.1
4.4.2
4.1.1
4.4.1
4.4.1
4.4.2
2.1.4
2.2
2.1.4
2.1.4
2.1.4
4.1.1
3.2
4.2.2
Refer to the I/O Module