Installation Standard Work Checklist - Heat & Glo MEZZO-1000-AU Installation Manual

Hide thumbs Also See for MEZZO-1000-AU:
Table of Contents

Advertisement

Installation Standard Work Checklist

This standard work checklist is to be used by the installer in conjunction with, not instead of, the instructions contained in this
installation manual.
Customer:
Lot/Address:
Model (circle one): MEZZO-1000-AU, MEZZO-1300-AU,
MEZZO-1600-AU, MEZZO-1300ST-AU
WARNING! Risk of Fire or Explosion! Failure to install appliance according to these instructions
can lead to a re or explosion.
Appliance Install Sections 3 and 6
fi
Veri
ed that the chase is insulated and sealed. (Pg. 12) Required factory-
installed non-combustible board is in place. Veri
combustibles. (Pg. 11,13,14) Fireplace is leveled and secured. (Pg. 30)
Pipe heat shield is attached to header. Header no wider than 3.5 in.(2x4)
(Pg. 29)
Venting/Chimney Sections 4,5 and 7
Venting con
fi
guration complies to vent diagrams. (Pg. 18-25) Venting
installed, locked, and secured in place with proper clearance. Firestops
installed. (Section 5)
Attic insulation shield installed. (Pg. 27)
fl
Exterior wall/Roof
ashing installed and sealed. (Section 7) Terminations
installed and sealed. (Section 7)
Electrical Section 8 (Pg 37-38)
Unswitched power (220/240 VAC) provided to the appliance. Switch wires
properly installed.
Gas Section 9 (Pg 39-42)
Proper appliance for fuel type.
Was a conversion performed?
Leak check performed and inlet pressure veri
fi
Veri
ed proper air shutter setting for installation type.
Finishing Section 10 (Pg 43-49)
Combustible materials not installed in non-combustible areas.
Veri
fi
ed all clearances meet installation manual requirements.
Finishing done correctly using inside
Finishing template removed.
Mantels and wall projections comply with installation manual requirements.
Appliance Setup Section 11 (Pg 50-51)
All packaging and protective materials removed (inside & outside of appliance).
Refractories and media installed correctly.
Glass assembly installed and secured.
Accessories installed properly.
Decorative front properly installed.
Manual bag and all of its contents are removed from inside/under
the appliance and given to party responsible for use and operation.
Started appliance and veri
Lights work in all switched positions (if so equipped).
Component heat shield is installed. (Pg. 38)
Hearth & Home Technologies recommends the following:
 Photographing the installation and copying this checklist for your fi
 That this checklist remain visible at all times on the appliance until the installation is complete.
Comments:
Further description of the issues, who is responsible (Installer/ Builder/ Other Trades, etc) and corrective
action needed
Comments Communicated to party responsible _____________________ by _______________________ on
= Contains updated information.
Heat & Glo • MEZZO-1000-AU, MEZZO-1300-AU, MEZZO-1300ST-AU, MEZZO-1600-AU Installation Manual • 2304-970 Rev. D • 3/15
ATTENTION INSTALLER:
Follow this Standard Work Checklist
fi
ed clearances to
fi
ed.
fi
t or overlap
fi
t method.
fi
ed no gas leaks exist.
(Builder / Gen. Contractor/) (Installer)
Date Installed:
Location of Fireplace:
Installer:
Dealer/Distributor Phone # ____________________
Serial #:
YES
IF NO, WHY?
le.
(Date)
2304-972 Rev. B 2/15
3

Advertisement

Table of Contents
loading

This manual is also suitable for:

Mezzo-1300st-auMezzo-1300-auMezzo-1600-au

Table of Contents