63 9810.0293 - Rev.00 - 08/09/2008
Location of the device must be done in accordance
with CE,national standards and local regulations to
ambients that air current exists.
The open expansion tank must be connected to the
boiler. The closed expansion tanks are very dangeorus
for solid fuel boilers. If closed expansion tank is used,
the boiler will be out of warranty. The diameter of the
open expansion tank connection pipe must be same
with the boiler connection pipe's.
tank connection pipes must be steel installation pipe not
plastic. The usage of the plastik installation pipe on
expansion tanks is very dangerous and in this case the
boiler will be out of warranty.
To fill and drain water to the boiler, you must mount
a valve.
You should isolate all the installation pipes to
prevent heat loss.
Make the boiler electricity connection to the
grounding plug.
In case of power cut, never load coal to the boiler.
Mount the circulating pump on the inlet pipe of the
boiler and connect the cable to the electrical terminal of
the pump.
Mount the circulating pump as the below:
The vertical assembly of the pump shaft causes wearing
of rotor bearing rapidly. So, the vertical assembly of the
pump shaft must'nt make.