Settle the boiler onto concrete base. Ambient
where is boiler in should not be dusty and moist.
*The boiler should be placed onto the concrete
base.
*The size of the concrete base is shown on the
table.
*After placing the boiler on to base, it should be
balanced from the ground surface.
Caution! Waste gas way must be as short as
possible. Waste gas pipes must be installed as in
slanting direction towards chimney and connections
must have full imperviousness.
The chimney must be designed considering
technical specifications determined in DIN 4705 and
built according to DIN 18160.