PRESSURE TESTING:
The pressures listed on the previous page can be tested using a manometer.
To attach manometer, first remove the inspection cover from back panel. The cover is
located directly behind the control and is removed by unscrewing the two top screws.
This will expose the back of the control so manometer tubes can be attached to the
pressure taps as shown below.
The inlet pressure can be adjusted via in line regulators in the supply to the heater, and
the outlet (operating) pressure by adjusting the valves internal regulator. To locate the
valves regulator adjustment screw the plastic control cover must be removed from the
front of the valve. This is done by removing the bottom screw and inserting a small flat
head screwdriver into the slot at the top on the front of this cover and pulling the cover
off.
Refer to fig. 4 below
CONNECTING THE FAN
The fan should be connected to the mains supply (240V 50Hz) via the 3m flex and 3pin
plug provided.