2. Install Powerhead bolts. Torque to 28 lb.ft. (38.0 N·m).
3. Install cover. Torque bolts to 80 lb. in. (9.0 N·m).
4-36 - POWERHEAD
4. Reattach ground wire to powerhead. Connect wires
from trim relay switch. Connect tel tale hose.
Design 1
b
Design 2
b
PE-51088
a
a - Module(s)
b - Ground Lead
c - Tel Tale Hose
5. Reconnect wires and oil hose. Secure in place with sta-
strap.
a - Oil Tank Wires
PE-51083
b - Power Trim Wires
c - Oil Hose (Connect to Tank)
a
c
a
b
90-817643R1 DECEMBER 1996
c
PE-51082
c
54244
PE-51088