8. Remove PTO input shaft from PTO housing:
A. Shift PTO to "ON" position.
B. Remove two (2) retaining rings (items 1 and 2)
from PTO housing.
C. Slide input shaft assembly (item 3) toward PTO
shaft side.
D. Remove bearing (item 4).
E. Slide input shaft toward other side.
F. Remove bearing (item 5).
G. Remove thrust washer (item 6) and gear (item 7),
sliding input shaft toward PTO shaft side.
H. Release shift arm (item 8) from shifter block (item
9).
I. Remove input shaft assembly.
9. Disassemble PTO input shaft:
A. Remove shift collar (item 1).
B. Remove two (2) steel balls (item 2) and spring
(item 3).
Drive Train
1
Page 6 - - 56
Moly disulfide
grease
Figure 118
8
6
7
Figure 119
2
3
2
Figure 120
Workman HD Series
3