Table 8: E320 Router PDU Cables and Wires Needed
Cable/Wire
One 6-AWG ground wire
Two 4-AWG wire leads
Two 4-AWG wire leads

Task 1: Turn Off All Router Power

Copyright © 2010, Juniper Networks, Inc.
From
PDU ground terminal
PDU Power A –48 VDC and RTN leads
PDU Power B –48 VDC and RTN leads
Figure 27 on page 51 shows the main components of a PDU.
Figure 27: PDU
Before starting to cable the router, push all router power switches to OFF to turn off the
router.
Chapter 5: Cabling the Router
To
Termination ground
Appropriate leads on power source No.1
Appropriate leads on power source No.2