Figure 4-18. Thermal Sensor Terminal Location - Eaton 93PM UPS Installation And Operation Manual

20–50 kw (480v four wire) – 50 kw frame
Table of Contents

Advertisement

12. If wiring generator interface connections, proceed to paragraph 4.7 .4; if wiring external parallel CAN
connections, proceed to paragraph 4.7 .5; if wiring external parallel pull chain connections, proceed to
paragraph 4.7 .6; if wiring Minislot connections, proceed to paragraph 4.7 .7; if wiring REPO connections,
proceed to paragraph 4.8; otherwise, proceed to Step 13.
13. Reinstall all safety shield panels previously removed and secure with the retained hardware.
14. If removed, reinstall the sidecar front panel and secure with the retained hardware.
15. Close the UPS outside door and secure the latch.

Figure 4-18. Thermal Sensor Terminal Location

Eaton 93PM UPS (20–50 kW, 480V Four Wire – 50 kW Frame) Installation and Operation Manual P-164000540—Rev 4
Battery Detect and Shunt Trip
Terminals (See Figure 4-19 for
terminal assignments.)
www.eaton.com/powerquality
UPS System Installation
4-21