Chapter 8 Final tasks
Section 8.1 Final tasks
•
•
•
•
•
•
•
10
EVISION
Ready the system for normal customer operation.
It is recommended to plug in the system and allow it to reach full charge.
Remove trash, remove installation equipment and tools, clean up the installation area, and
store the service manuals.
Complete product locator cards and return them.
Record the installation time in the Service database.
Create specified login and user management account and password information to system
administrator. The account must be satisfied with all of the three roles: Administrator/Standard
User/Limited User.
Provide the below account and password information to system administrator.
-
Login and user management (Specially created account and password for system
administrator)
-
Installing the operator manual
-
IP change procedure