Commissioning, inspection, maintenance
Commissioning the heating system
Setting buffer charging up to buffer temperature
Available if the number of buffer temperature sensors
selected was
0.
>
Press the following buttons:
1.
/
for the required charging temperature of the
|
~
heating water buffer cylinder.
Selecting an additional boiler
Available if "No" was selected for the cascade.
Press the following buttons:
1.
/
"Yes" or "No" for the additional heat gener-
|
~
ator.
Setting buffer charging up to buffer temperature sensor
Available if previously:
■
Buffer temperature sensor "3", "4" or "5"
and
Additional boiler "Yes"
■
were selected.
Press the following buttons:
1.
/
Heating water buffer cylinder charging up to
|
~
the temperature sensor of the heating water
buffer cylinder "0", "1", "2", "3", "4" or "5".
Setting the buffer charging temperature by an additional boiler
Available if buffer charging by additional boiler up to
buffer temperature sensor
Press the following buttons:
1.
/
for the required charging temperature of the
|
~
heating water buffer cylinder.
Selecting parallel mode for additional boiler
Available if "Yes" was selected for additional boiler.
Press the following buttons:
1.
/
for parallel mode "Yes" or "No".
|
~
62
0 was selected.
>
(cont.)
2.
to confirm.
d
2.
to confirm.
d
2.
to confirm.
d
2.
to confirm.
d
2.
to confirm.
d