5 5
Vent Clearances and Vent Framing
A. Vent Clearances to Combustibles
WARNING! Risk of Fire! Maintain air space clearance
to vent. DO NOT pack insulation or other combustibles:
• Between ceiling firestops
• Between wall shield firestops
• Around vent system
Failure to keep insulation or other material away from
vent pipe could cause overheating and fire.
Note: Heat shields MUST overlap by a minimum of 1-1/2 in. (38 mm).
• DVP heat shield - designed to be used on a wall 4 in. to 7-1/4 in. (102 mm to 184
mm) thick.
• If wall thickness is less than 4 in. the existing heat shields must be field trimmed. If
wall thickness is greater than 7-1/4 in. a DVP-HSM-B will be required.
• SLP heat shield - designed to be used on a wall 4-3/8 in. to 7-5/8 in. (111 mm to
194 mm thick).
• If wall thickness is less than 4-3/8 the existing heat shields must be field trimmed.
If wall thickness is greater than 7-5/8 in. a DVP-HSM-B will be required.
(DVP-SLP Pipe Shown)
Heat
Shield
3 in. (76 mm)
top clearance
1 in. (25 mm)
clearance around
vertical sections
Heat
Shield
* When using SLP pipe, minimum clearances from the vent pipe to combustible materi-
als at inside wall firestops are:
Figure 5.1 Horizontal Venting Clearances To Combustible
Materials
Heat & Glo • SL-5/5LP-IFT, SL-7/7LP-IFT, SL-9/9LP-IFT Installation Manual • 2632-980 Rev. E • 4/21
3 in. (76 mm)
top clearance *
Heat
Shield
1 in. (25 mm)
clearance
Wall
bottom & sides
Shield
Firestop
WALL
3 in. (76 mm)
top clearance *
Heat
Shield
1 in. (25 mm)
Wall
clearance
Shield
bottom & sides
Firestop
WALL
Top: 2-1/2 in. (64 mm)
Bottom: 1/2 in. (13 mm)
Sides: 1 in. (25 mm)