First Startup With A New Program Module Or In Case Of Replacement Of Program Module - Siemens LME7 Series Basic Documentation

Burner control
Hide thumbs Also See for LME7 Series:
Table of Contents

Advertisement

Alternately
nfo
>3 s
Alternately
Alternately
Building Technologies Division
Infrastructure & Cities Sector
25.6
First startup with a new program module or
in case of replacement of program module
After 2 minutes, the unit changes to Loc 138
Basic Documentation LME7...
25 Operation via internal LED
Display shows alternately rSt and PrC.
Display shows the replacement of the program module.
Signal lamp blinks red once and yellow twice alternately.
nfo
Press
for >3 seconds to start data download from the
program module.
Signal lamp blinks yellow.
The process of 3 seconds is supported by a short flash of
the yellow signal lamp.
Note:
nfo
If you press
for <3 seconds, data download does not
start. To start the restore process again, the LME7... must
be reset by switching mains ON/OFF.
Display shows run during download (restore process) of the
program sequence.
Display shows alternately End and rSt.
Display shows the end of data exchange.
Signal lamp blinks red.
After the restore process, the unit is automatically in
the lockout position (LOC 138) and must be reset for
operation!
213/245