INITIAL START-UP

After the control panel has been programmed and the
compressor heater has been on for 24 hours prior to
start-up, the chiller may be placed into operation.
$
1. Place the System Switches on the Micropro-
cessor Board to the ON position.
$
2. The compressor will start and a flow of refrig-
erant will be noted in the sight glass. After sev-
eral minutes of operation, the bubbles in the
sight glass will disappear and there will be a
solid column of liquid when the TXV stabilizes.
After the water temperature stabilizes at desired
operating conditions, the oil should be clear.
$
3. Allow the compressor to run a short time, being
ready to stop it immediately if any unusual noise
or adverse conditions develop. Immediately at
start-up, the compressor will make sounds dif-
ferent from its normal high pitched sound. This
is due to the compressor coming up to speed
and lubrication changing from liquid refriger-
ant to oil. This should be of no concern and lasts
for only a short time.
$
4. Check the system operating parameters. Do this
by selecting various displays such as pressures
and temperatures. Compare these to test gauge
readings.

CHECKING SUBCOOLING AND SUPERHEAT

The subcooling should always be checked when charg-
ing the system with refrigerant and/or before setting
the superheat.
When the refrigerant charge is correct, there will be
no bubbles in the liquid sight glass with the system
operating under full load conditions, and there will be
6 - 8°C (10 - 15°F) subcooled liquid leaving the con-
denser. An overcharged system should be guarded
against. Evidences of overcharge are as follows:
a. If a system is overcharged, the discharge pressure
will be higher than normal. (Normal discharge/con-
densing pressure can be found in the refrigerant tem-
perature/pressure chart; use entering air temperature
+ 17°C (30°F) for normal condensing temperature.
b. The temperature of the liquid refrigerant out of the
condenser should be not be more than 8°C (15°F)
less than the condensing temperature (The tempera-
ture corresponding to the condensing pressure from
the refrigerant temperature/pressure chart).
YORK INTERNATIONAL
The subcooling temperature of each system should be
calculated by recording the temperature of the liquid
line at the outlet of the condenser and subtracting it
from the recorded liquid line pressure at the liquid stop
valve, converted to temperature from the temperature/
pressure chart.
Example:
Liquid line pressure =
202 PSIG converted to
minus liquid line temp.
SUBCOOLING =
The subcooling should be adjusted to 7 - 8°C (12 - 15°F).
$
1. Record the liquid line pressure and its corre-
sponding temperature, liquid line temperature
and subcooling below:
SYS 1
Liq Line Press =
Temp =
Liq Line Temp =
Subcooling =
After the subcooling is set, the suction superheat should
be checked. The superheat should be checked only af-
ter steady state operation of the chiller has been estab-
lished, the leaving water temperature has been pulled
down to the required leaving water temperature, and
the unit is running in a fully loaded condition. Correct
superheat setting for a system is 6 - 7°C (10 - 12°F).
The superheat is calculated as the difference between
the actual temperature of the returned refrigerant gas
in the suction line entering the compressor and the tem-
perature corresponding to the suction pressure as shown
in a standard pressure/temperature chart.
Example:
Suction Temp =
minus Suction Press
60 PSIG converted
to Temp
The suction temperature should be taken 13 mm (6")
before the compressor suction service valve, and the
suction pressure is taken at the compressor suction ser-
vice valve.
FORM 201.18-NM6
39°C (102°F)
31°C (- 87°F)
8°C
(15°F)
SYS 2
kPa (PSIG)
°C
(°F)
°C
(°F)
°C
(°F)
8°C (46°F)
1°C (-34°F)
=
7°C (12°F)
95