21 - START-UP CHECKLIST FOR 30RQS/30RQSY HEAT PUMPS
(USE FOR JOB FILE)
Preliminary information
Job name: ................................................................................................................................................................................................
Location: ..................................................................................................................................................................................................
Installing contractor: ................................................................................................................................................................................
Distributor: ...............................................................................................................................................................................................
Start-up performed by:.................................................................. 
Equipment
Model 30RQS/RQSY: ......................................................................
Compressors
Circuit A
1.  Model No.  ..............................................................................   1.    M odel No. ................................................................................
Serial No.  ...............................................................................  
2.  Model No. ...............................................................................   2.    M odel No. ................................................................................
Serial No. ................................................................................  
3.  Model No. ...............................................................................
Serial No. ................................................................................
Air handling equipment
Manufacturer ...........................................................................................................................................................................................
Model No.  ................................................................................... 
Additional air handling units and options .................................................................................................................................................
.................................................................................................................................................................................................................
Preliminary equipment check
Is there any shipping damage? .................................................... 
.................................................................................................................................................................................................................
Will this damage prevent unit start-up? ...................................................................................................................................................
 Unit is level in its installation
 Power supply agrees with the unit name plate
 Electrical circuit wiring has been sized and installed properly
 Unit ground wire has been connected
 Electrical circuit protection has been sized and installed properly
 All terminals are tight
 All cables and thermistors have been inspected for crossed wires
 All plug assemblies are tight
Check air handling systems
 All air handlers are operating
 All chilled water valves are open
 All fluid piping is connected properly
 All air has been vented from the system
 Chilled water pump is operating with the correct rotation. CWP amperage: Rated: ...........................   Actual............ ....
Unit start-up
 Water pump control has been properly interlocked with the heat pump
 Oil level is correct
 Compressor crankcase heaters have been energised for 12 hours
 Unit has been leak checked (including fittings)
 Locate, repair, and report any refrigerant leaks
.................................................................................................................................................................................................................
.................................................................................................................................................................................................................
Check voltage imbalance: AB .....................  AC ..................   BC ..................
Average voltage =  .....................................  (see installation instructions)
Maximum deviation =  ................................  (see installation instructions)
Voltage imbalance =  ..................................  (see installation instructions) ...
 Voltage imbalance is less than 2%
WARNING: Do not start the unit if voltage imbalance is greater than 2%. Contact local power company for assistance.
 All incoming power voltage is within rated voltage range
56
Date:  ...........................................................................................
S/N ...............................................................................................
Circuit B
    S erial No. ................................................................................
    S erial No. ................................................................................
Serial No. .....................................................................................
If so, where? ................................................................................

Advertisement

Table of Contents
loading

Table of Contents