These  products  incorporate  equipment  or  components  under 
pressure,  manufactured  by  Carrier  or  other  manufacturers.  We 
recommend  that  you  consult  your  appropriate  national  trade 
association or the owner of the equipment or components under 
pressure  (declaration,  re-qualification,  retesting,  etc.).  The 
characteristics of this equipment/these components are given on 
the nameplate or in the required documentation, supplied with the 
products.  These  units  comply  with  the  European  Pressure 
Equipment Directive.
The units are intended to be stored and operate in an environment 
where the ambient temperature must not be less than the lowest 
allowable temperature indicated on the nameplate.
Do not introduce high static and dynamic pressure compared with 
the existing operating pressures - either service or test pressures 
- in the refrigerant circuit or in the heat transfer circuit, especially:
• limiting the elevation of the condensers or evaporators
• taking the circulating pumps into consideration.

1.5 - Maintenance safety considerations

Carrier recommends the following drafting for a logbook (the table 
below should not be considered as reference and does not involve 
Carrier responsibility):
Name of the
Intervention
commissioning
Date
Nature
(1)
engineer
(1)  Maintenance, repairs, regular verifications (EN 378), leakage, etc.
Engineers  working  on  the  electric  or  refrigeration  components 
must  be  authorized,  trained  and  fully  qualified  to  do  so  (e.g. 
electricians trained and qualified in accordance with IEC 60364 
Classification BA4).
All refrigerant circuit work must be carried out by a trained person, 
fully qualified to work on these units. He must have been trained 
and be familiar with the equipment and the installation. All welding 
operations must be carried out by qualified specialists.
Aquasnap  units  use  high-pressure  R-410A  refrigerant  (the  unit 
operating  pressure  is  above  40  bar,  the  pressure  at  35°C  air 
temperature is 50% higher than for R-22). Special equipment must 
be used when working on the refrigerant circuit (pressure gauge, 
charge transfer, etc.).
Any manipulation (opening or closing) of a shut-off valve
must be carried out by a qualified and authorised engineer,
observing applicable standards (e.g. during draining
operations). The unit must be switched off while this is done.
NOTE: The unit must never be left shut down with the liquid
line valve closed, as liquid refrigerant can be trapped between
this valve and the expansion device and lead to the risk of a
pressure increase. This valve is situated on the liquid line
before the filter drier box.
Equip the engineers that work on the unit as follows:
Personal protection
equipment (PPE)
(1)
Handling
Protective gloves,
eye protection,
safety shoe,
protective clothing.
Ear protection.
Filtering respirator.
(1)  We recommend to follow the instructions in EN 378-3.
(2)  Performed in the presence of A1 refrigerant according to EN 378-1.
6
Applicable
Verification
national
Organism
regulations
Operations
Maintenance,
Welding or
service
brazing
x
x
x
x
x
x
x
x
Never work on a unit that is still energized. Never work on
any of the electrical components, until the general power
supply to the unit has been cut.
If any maintenance operations are carried out on the unit,
lock the power supply circuit in the open position and secure
the machine upstream with a padlock.
If the work is interrupted, always ensure that all circuits are
still deenergized before resuming the work.
ATTENTION: Even if the unit has been switched off, the power
circuit remains energized, unless the unit or customer circuit
disconnect switch is open. Refer to the wiring diagram for
further details. Attach appropriate safety labels.
If any work is carried out in the fan area, specifically if the
grilles or casings have to be removed, cut the power supply
to the fans to prevent their operation.
It is recommended to install an indicating device to show if
part of the refrigerant has leaked from the valve. The presence
of oil at the outlet orifice is a useful indicator that refrigerant
has leaked. Keep this orifice clean to ensure that any leaks
are obvious. The calibration of a valve that has leaked is
generally lower than its original calibration. The new
calibration may affect the operating range. To avoid nuisance
tripping or leaks, replace or re-calibrate the valve.
OPERATING CHECKS:
Important information regarding the refrigerant used:
This product contains fluorinated greenhouse gas covered
by the Kyoto protocol.
Fluid type: R410A
Global Warming Potential (GWP): 2088
CAUTION:
1. Any intervention on the refrigerant circuit of this product
should be performed in accordance with the applicable
legislation. In the EU, the regulation is called F-Gas,
N°517/2014.
2. Ensure that the refrigerant is never released to the
atmosphere during installation, maintenance or equipment
disposal.
3. The deliberate gas release into the atmosphere is not
allowed.
4. If a refrigerant leak is detected, ensure that it is stopped
and repaired as quickly as possible.
5. Only a qualified and certified personnel can perform
installation operations, maintenance, refrigerant circuit
leak test as well as the equipment disposal and the
refrigerant recovering.
6. The gas recovery for recycling, regeneration or destruction
is at customer charge.
7. Periodic leak tests have to be carried out by the customer
or by third parties. The EU regulation set the periodicity
here after:
System WITHOUT
leakage detection
System WITH leakage
detection
Refrigerant charge/
circuit (CO
equivalent)
2
(2)
R134A
(GWP 1430)
R407C
(GWP 1774)
R410A
(GWP 2088)
HFO's: R1234ze
(1)   From 01/01/2017, units must be equipped with a leakage detection system
No Check 12 Months 6 Months
No Check 24 Months 12 Months
5 ≤
50 ≤
< 5 Tons
Charge
Charge
< 50 Tons
< 500 Tons
3.5 ≤
34.9 ≤
Charge
Charge
Charge
< 3.5 kg
< 34.9 kg
< 349.7 kg
2.8 ≤
28.2 ≤
Charge
Charge
Charge
< 2.8 kg
< 28.2 kg
< 281.9 kg
2.4 ≤
23.9 ≤
Charge < 
Charge
Charge
2.4 kg
< 23.9 kg
< 239.5 kg
No requirement
3 Months
6 Months
Charge
> 500 
Tons
(1)
Charge
> 349.7 kg
Charge
> 281.9 kg