Start-Up Checklist For 61Af Heat Pumps (Use For Job File) - Carrier AquaSnap 61AF 022 Installation, Operation And Maintenance Instructions

High-temperature heat pumps
Table of Contents

Advertisement

16 - START-UP CHECKLIST FOR 61AF HEAT PUMPS (USE FOR JOB FILE)

Preliminary information
Job name : ...............................................................................................................................................................................................
Location : .................................................................................................................................................................................................
Installing contractor : ...............................................................................................................................................................................
Distributor : ..............................................................................................................................................................................................
Start-up preformed by :.................................................................
Equipment
Model 61AF : ................................................................................
Compressors
1. Model No. ...............................................................................
Serial No. ................................................................................
Air handling equipment
Manufacturer ...........................................................................................................................................................................................
Model No ......................................................................................
Additional air handling units and accessories..........................................................................................................................................
.................................................................................................................................................................................................................
Preliminary equipment check
Is there any shipping damage ? ...................................................If so, where? ......................................................................................
.................................................................................................................................................................................................................
Will this damage prevent unit start-up? ...................................................................................................................................................
Unit is level in its installation
Power supply agrees with the unit name plate
Electrical circuit wiring has been sized and installed properly
Unit ground wire has been connected
Electrical circuit protection has been sized and installed properly
All terminals are tight
All cables and thermistors have been inspected for crossed wires
All plug assemblies are tight
Check air handling systems
All air handlers are operating
All water valves are open
 All fluid piping is connected properly
All air has been vented from the system
Hot-water pump is operating with the correct rotation. CWP amperage: Rated : ................................................... Actual............
Unit start-up
Hot-water pump control has been properly interlocked with the heat pump
Oil level is correct
Compressor crankcase heaters have been energised for 12 hours
 Unit has been leak checked (including fittings)
Locate, repair, and report any refrigerant leaks
.................................................................................................................................................................................................................
.................................................................................................................................................................................................................
Check voltage imbalance : AB ......................................................AC............................... BC ..........................
Average voltage = .......................................................................(see installation instructions)
Maximum deviation = ..................................................................(see installation instructions)
Voltage imbalance = ....................................................................(see installation instructions)
Voltage imbalance is less than 2%
WARNING: Do not start the heat pump if voltage imbalance is greater than 2%. Contact local power company for assistance.
All incoming power voltage is within rated voltage range
Date: ............................................................................................
S/N ...............................................................................................
.2.
Model No .............................................................................
Serial No ..............................................................................
Serial No .....................................................................................

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents