Z100-TYPE HARDWARE
"X" Connector Label
The label shown in Figure 2-40 is installed between terminal rows 5C and "X" on the CAP.
The top half of the label identifies system port circuit appearances on the 5C connector that
are used for voice terminals used for both emergency transfer stations and normal
extensions. The bottom half of the label identifies the connection to the cross-connect field
for voice terminals used only for emergency transfer.

Installing the Sneak Fuse Panels

Install the sneak fuse panels as near as possible to the network interface. The fuse panel
has two mounting screw slots. To install the panel, proceed as follows:
1 . Hold the panel against the mounting surface and mark the upper right and lower
left mounting screw locations and remove panel.
2 . Drill pilot holes at the marked locations and partially install the screws.
3 . Slide the panel onto the mounting screws and tighten.
4 . Repeat the procedure for each additional sneak fuse panel.

Cable Installation

Labels
The port label shown in Figure 2-41 is installed on both ends of the 25-pair main cross-
connect field and the cable access panel. The blue/yellow building and floor labels are
optionally used for cables that connect from the equipment room to a site or satellite
location located on another floor or in another building. An additional yellow port label is
shown. This yellow label is used for auxiliary circuits that connect to the cable access panel
or SSI circuits that connect to an Applications Processor.
2-60
Figure 2-40. "X" Connector Label