Initial Startup; Ups Startup; Unirom Setup And Operation; Setup Instructions - Eaton 9355-F47 Unirom User Manual

10/15 kva
Table of Contents

Advertisement

OPERATION
Table 10. User Settings (continued)
Description
Reset Custom Event Settings
Auto Output Configuration

Initial Startup

UPS Startup

Unirom Setup and Operation

78
Eaton 9355-F47 Unirom UPS (10/15 kVA) User's Guide
Available Settings
0 through 32
Enabled/Disabled
Startup and operational checks must be performed by an authorized
Eaton Customer Service Engineer, or the warranty terms as specified on
page W-105 become void. This service is offered as part of the sales
contract for the UPS. Contact service in advance (usually a two-week
notice is required) to reserve a preferred startup date.
Only qualified service personnel (such as a licensed electrician) should perform the UPS
installation and initial startup. Risk of electrical shock.
Verify that UPS installation has been carried out correctly and the UPS
ground has been connected.

Setup Instructions:

1. Connect input and output cables. *See user manual for
recommended minimum cable size and quantity.
2. Connect battery string or Ultracapacitor to the UPS/PFU.
3. If no remote EPO/EMO scheme is used. Leave jumper on remote
EMO switch (TB5) terminal strip and DO NOT connect wires to 24V
EMO (TB4) terminal strip.
Additional setup for optional remote EPO/EMO scheme:
Default Setting
Total: 0/32
Enabled for initial startup
Disabled after initial startup
W A R N I N G
S
164201642 Rev C www.eaton.com/powerquality

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents