4.7
Initial Startup
Startup and operational checks for parallel systems or installations with accessory cabinets must be performed
by an authorized Eaton Customer Service Engineer, or the warranty terms may become void. This service is
offered as part of the sales contract for the UPS. Contact an Eaton service representative in advance (usually
required three days) to reserve a preferred startup date.
4.8
Completing the Installation Checklist
The final step in installing the UPS system is completing the following Installation Checklist. This checklist
ensures that you have completely installed all hardware, cables, and other equipment. Complete all items listed
on the checklist to ensure a smooth installation. Make a copy of the Installation Checklist before filling it out,
and retain the original.
After the installation is complete, an Eaton Customer Service Engineer must verify the operation of the UPS
system and commission it to support the critical load. The service representative cannot perform any
installation tasks other than verifying software and operating setup parameters. Service personnel may request
a copy of the completed Installation Checklist to verify all applicable equipment installations have been
completed.
37
NOTE
The Installation Checklist MUST be completed prior to starting the UPS system for
the first time.
Eaton 93E MK2 UPS (10-40kVA, 380/400/415V) Installation and Operation