7. Connect the wires from the electronics module (already routed to
8. Reinstall the internal cover panel.
9. Replace the UPS lower front cover.
10. Continue to one of the following sections:
Eaton 9355-F47 Unirom UPS (10/15 kVA) User's Guide
the front of the UPS) to the ultracapacitor module terminals, as
described below (see Figure 27):
Route the wire with the red connector through the bushing to the
bottom shelf. Connect the red connector to the red connector on
the ultracapacitor module cable.
Route the remaining cable with the black connector through the
bushing to the bottom shelf. Connect the black connector from the
electronics module to the internal socket connector on the
ultracapacitor module.
S
"Communication" on page 55 to install UPS communication
options, such as X-Slot cards.
S
"Operation" on page 73 to start up the UPS. Remove the
lockout/tagout devices before starting up the UPS.
S
164201642 Rev C www.eaton.com/powerquality
ULTRACAPACITOR MODULE INSTALLATION