Fig.50
8
8
Fig.51
>200 kg
7702630 - v02 - 11082018
7. Screw the lifting rings into the locations provided. Tightening torque:
7
8. Remove the screws attaching the boiler to the pallet.
8
8
MW-4000298-1
9. Use slings (not provided) to move the boiler.
10. Close the boiler.
9
MW-4000299-1
23 N.m.
Important
The rings are supplied with the boiler.
Sling attachment angle
POWER HT+ 1.200
POWER HT+ 1.250
Caution
Moving the boiler is a job for two people.
5 Before installation
β < 60°
212 kg
232 kg
POWER HT +
43