2.4.2 Putting into operation of CM EIB/KNX

1. Bus voltage and supply voltage must be present.
2. Connect the PC to the serial EIB interface.
3. Start software ETS, using ETS2 version 1.2.
4. Configure the application program in ETS2, V 1.2.
5. The application program is loaded into the devices via
the EIB interface. The application program is available
on the LOGO! home page (http://www.siemens.de/logo).
6. Click on "Program Physical Address" in ETS.
7. Press the button of the CM EIB/KNX to switch the CM
EIB/KNX to programming mode; LED lights up orange.
Note
The button "Prog ↓" should not be pressed too firmly.
If the bus connection is OK, the LED lights up green.
In programming mode, the LED lights up orange.
8. If the LED is extinguished, the programming of the
physical address has finished. You can now mark the
physical address on the device. Composition of the
physical address:
Area / Line / Device XX / XX / XXX
9. The application program can now be run. The device is
then ready for operation.
10.If several CM EIB/KNX are installed in an EIB system,
steps 1 to 9 must be repeated for each CM EIB/KNX.
11. Any further details about EIB commissioning can be
found in the corresponding documentation.

2.4.3 Operating states

LOGO! Basic operating states
LOGO! Basic/Pure knows two operating states: STOP and
RUN.
LOGO! Manual
A5E00380835-01
LOGO! installation and wiring
49