LOGO! installation and wiring
2.4 Putting into operation
Note
When a power failure occurs while you are entering a circuit program, the program in LOGO!
will be deleted after power is returned.
Before you modify the circuit program, save a backup copy of your original to a memory
card, a combined memory/battery card, or to a computer (using LOGO!Soft Comfort).
2.4.2

Putting a CM EIB/KNX into operation

1. Bus voltage and supply voltage must be present.
2. Connect the PC to the serial EIB interface.
3. Start software ETS, using ETS2 version 1.2.
4. Configure the application program in ETS2, V 1.2.
5. The application program is loaded into the devices via the EIB interface. The application
program is available on the LOGO! home page (http://www.siemens.de/logo).
6. Click on "Program Physical Address" in ETS.
7. Press the button of the CM EIB/KNX to switch the CM EIB/KNX to programming mode;
LED lights up orange.
Note
The button "Prog ↓ " should not be pressed too firmly.
If the bus connection is OK, the LED lights up green.
In programming mode, the LED lights up orange.
8. If the LED is extinguished, the programming of the physical address has finished. You
can now mark the physical address on the device. Composition of the physical address:
Area / Line / Device XX / XX / XXX
9. The application program can now be run. The device is then ready for operation.
10.If several CM EIB/KNX are installed in an EIB system, steps 1 to 9 must be repeated for
each CM EIB/KNX.
11.Any further details about EIB commissioning can be found in the corresponding
documentation.