6) Install Top Support Frame
Slide in the Top Support Frame using the slots as a guide. Secure
and re-tighten the screws to the unit.
View of backside of Top Support Frame.
7) Side Support Frame
a) Mount Side Support Frame to unit as shown in Diagram 6, then
secure with 2 screws on each side.
b) Repeat step on the other side.
Diagram 6
56
Cut-Outs
8) Attach Top and Side Support Frame
a) Ensure the Side Supports are aligned with the corresponding
hole on the Top Support Frame, then secure with 1 screw.
b) Repeat step on the other side.
Note: The Nailing Strips can be adjusted, depending on the facing
material (as indicated in Diagram 7).
1/2" Facing
Material
1" Facing
Material
Diagram 7
9) Optional
Install Optional Tripoli 3-Panel Arch Screen Door. (Refer to 3-Panel
Arch Door Instruction Sheet).
10) Change Logo
Replace existing logo with Regency logo.