11.6
Commissioning log
The Logano G515 can be used with an oil or gas-fired burner. Fill in the
commissioning log for the appropriate type of oil or gas burner carefully.
Commissioning operations
1.
Perform leak test of the entire system
2.
Fill the heating system with water
3.
Purge the air from the heating system
4.
Perform the leak test if the boiler was assembled on-site
5.
Record the filling water quantity and composition in the operator's log
(included with the technical documentation).
6.
Check position of heat exchanger baffles
7.
Check the fuel line for leaks.
8.
Start up the control panel
9.
Initial burner start-up
10.
Check the flue gas temperature
11.
Check vent pipe for leaks.
12.
Check the boiler and flue gas side for leaks
13.
Enter the fuel used in the table provided in the operating instructions.
14.
Inform the owner and operator and hand over technical documentation
15.
Confirm properly-completed commissioning
Company stamp/signature/date
Logano G515 – 6 720 647 208 (2014/09)
▶ Sign all start-up work as completed and enter the relevant date.
Individual steps
page 35
page 19
page 22
page 35
See burner
documentation
page 36
11
System start-up
Comments (signature)
37