Commissioning log

V Initial and date the commissioning operations carried
out.
Commissioning operations
1.
Fill heating system and check for leaks
– Heating system pressure
2.
Fill trap with water
3.
Bringing the system up to operating pressure
V Bleeding heating system
V Testing relief valve
V Adjust the expansion vessel pressure (
umentation)
4.
Checking combustion air supply and flue system
5.
Checking position of heat exchanger baffles
6.
Documentation
7.
Start up the burner (
8.
Checking the manual reset high limit (STB)
9.
Adjust the programming unit settings to suit the customer's
requirements (
programming unit documentation)
10. Inform operator, hand over technical documentation
Confirmation of properly completed commissioning
Tab. 14
Inform the customer about the correct fuel
and correct operating pressure. Enter the de-
tails in the table (
tions).
Logano GB125 BE US/CA - Technical specifications are subject to change without prior notice.
expansion vessel doc-
burner documentation)
boiler operating instruc-
Placing the heating system in operation
Page
Readings taken
26
____________ psi
33
____________ psi
34
34
34
36
Company stamp/signature/date
6
Comments