Summary of Contents for Buderus Logano G315
Page 1
These instructions are available in English and French. Please keep these instructions for future reference. Installation and Service Instructions Logano G315 Boilers for oil/gas-fired power burners Please read carefully prior o installation and maintenance.
▶ Only employ a trained and certified contractor to carry out work on the gas train. Explosive and easily combustible materials Never use or store easily combustible materials (paper, thinners, paints, etc.) near the appliance. Logano G315 – 6 720 817 939 (2017/02)
Natural Gas (NG) Remarks The Logano G315 boiler can be operated with the specified fuels. Select a burner suitable for use with the fuels specified for the Logano G315 boiler. The output figures shown in the Table “Technical Data” are nominal power figures.
The Logano G315 can be operated with oil, gas, and combination temperature. The controls can reduce the flow rate by closing the valves burners. For a list of the approved burners, please contact Bosch on the mixed heating circuits, modulating the boiler primary pumps, Thermotechnology Corp.
(c) MANUFACTURERS REQUIREMENTS - GAS EQUIPMENT VENTING SYSTEM REQUIRED. When the manufacturer of Product Approved side wall horizontally mounted gas equipment provides a venting system design or venting system components with the equipment, the Logano G315 – 6 720 817 939 (2017/02)
(155 mm) 7" (180 mm) 6 720 642 621-48.1o Fig. 3 Technical data for Logano G315 (dimensions in inches (mm)) Drain valve (Rp ¾) Boiler heat exchanger length Overall boiler length Return connection on the boiler Supply connection on the boiler 1) With the drain valve (EL), you may only drain the system, not fill it.
Example: Safety limit (STB) = 212 °F (100 °C), max. possible supply temperature = 212 – 32 = 180 °F (100 – 18 = 82 °C). Scope of delivery Transporting the boiler The Logano G315 can be delivered either as a pre-assembled block or in Use suitable equipment to transport the individual boiler sections loose sections.
Positioning the boiler Assembly Positioning the boiler tool(s) per Extension piece Length (total) in This chapter describes how to properly position the Logano G315. Boiler sections boiler hub per boiler hub inches (mm) 5...9 121-1/4 NOTICE: Risk of damage from freezing.
(Fig. 11, [2]) should protrude approx. 28 mm out of the corresponding hub once they have been driven in. ▶ Remove any burrs with a file. 720 42 21-05.1o Fig. 9 Remove burrs Logano G315 – 6 720 817 939 (2017/02)
Page 14
Once this ▶ Peel the backing paper from the sealant rope when inserting into the has been done, the boiler section can be aligned with the packing groove (do not stretch). lower hub. Logano G315 – 6 720 817 939 (2017/02)
Page 15
▶ Push mating flanges (Fig. 18, [1]) onto the tie rods (Fig. 18, [3]) and secure each with wedge (Fig. 18, [2]). ▶ Hold the tie rod in the center of the boiler hubs and slightly draw together the assembly tools using the clamping nut. Logano G315 – 6 720 817 939 (2017/02)
The following pages describe the installation of the supply pipe and ▶ Remove boiler assembly tool. sensor well. You must do both irrespective of whether the boiler is supplied pre-assembled or in separate sections. Logano G315 – 6 720 817 939 (2017/02)
▶ Slowly fill the boiler with water via the fill and drain connection. While doing this, purge the boiler via the boiler flow connection with purger. 720 42 21-17.1o Fig. 22 Fitting the sensor well Logano G315 – 6 720 817 939 (2017/02)
▶ When the heating system is in operation, do not fill it [2]) is required for connecting the supply at a later stage (Fig. 27, via the boiler fill & drain valve. Instead, use the fill [1]). valve on the system side. Logano G315 – 6 720 817 939 (2017/02)
The sealant rope joint should be located at the side (Fig. 31, [2]). ▶ Hook the burner door with the hinge lobes into the hinge pins. 720 42 21-22.1o Fig. 29 Rear section with fittings installed Logano G315 – 6 720 817 939 (2017/02)
58-1/4" (1480) to rear section with machine screws (M 8 x × 15). The folded edge of the upper crosswise tier bar must point towards the front. Table 11 Dimensions – thermal insulation Logano G315 – 6 720 817 939 (2017/02)
Before fitting the other parts of the cover, you must first install the control panel, route the capillary tubes to the sensor well and insert the sensor into the sensor well ( Chapter 9, page 25). Logano G315 – 6 720 817 939 (2017/02)
Page 23
6 720 817 939-02.1T Fig. 40 Fitting the front base rail ▶ Screw the top rear boiler panel (Fig. 41, [2]) to the back of the cover (Fig. 41, [1]) and the side panels. Logano G315 – 6 720 817 939 (2017/02)
(A) – min. 720 mm – from the draft diverter in the vent pipe. ▶ Fit the flue gas temperature sensor (Fig. 45, [2]) as described in the separate installation manual. Logano G315 – 6 720 817 939 (2017/02)
A permanent connection must be made in accordance with EN 50165 or (Logamatic 43..) (Fig. 47, [2]). the relevant national installation standard. ▶ Route the capillary tubes through the cable entry and unroll to the required length. Logano G315 – 6 720 817 939 (2017/02)
▶ Screw terminal cover (Fig. 46, [1]) with the two self-tapping screws Sensor well back into the control panel base (Fig. 51). Ensure good contact between the sensor surfaces and the sensor well to ensure good temperature transfer. Use the compensating spring. Logano G315 – 6 720 817 939 (2017/02)
Line 1 power (hot) Line 2 power (neutral) Limit control terminal Motor control terminal Oil valve Oil valve (on cleancut pump) TRANS Ignition transformer Valve control terminal ——— Factory Wiring ------ Wiring supplied by installer Logano G315 – 6 720 817 939 (2017/02)
Filling the system System start-up NOTICE: Risk of system damage from temperature You can connect various control panels to the Logano G315. The stresses. commissioning process for the different types of controls is similar. ▶ During operation, only fill the heating system via the fill valve on the system side.
11.6 Commissioning log The Logano G315 can be used with an oil- or gas-fired burner. Fill in the ▶ Sign all start-up work as completed and enter the relevant date. commissioning log for the appropriate type of oil or gas burner carefully.
You should have your customer's system serviced for the following reasons: You can connect control panels of the 4000 series to the Logano G315. The shutting down process for the different types of control panel is the • to achieve a high level of efficiency and to operate the system same.
Page 34
Fig. 61 Flue gas baffles, removing bottom. ▶ Remove bottom rear boiler panel. The various brush types available from Buderus (optional extras) are ▶ Loosen spring hooks below the flue outlet ( Fig. 35, page 22). shown in Fig. 62.
The operating pressure must be at least 15 psi (1 bar). ▶ Read the current operating pressure (psi) and temperature °F (°C) from the temperature/pressure gauge. ▶ If the operating pressure drops below 15 psi (1 bar), refill boiler water. Logano G315 – 6 720 817 939 (2017/02)
If during inspection work conditions are identified that require maintenance, this work must be performed on an as-required basis. If make-up water is added, the quality of this water must correspond to the specifications in the enclosed operating manual. Logano G315 – 6 720 817 939 (2017/02)
Page 37
Check safe and proper operation Confirm professional inspection Company stamp/ Company stamp/ signature signature Table 15 Date:____________ Date:____________ Date:____________ Date:____________ Company stamp/ Company stamp/ Company stamp/ Company stamp/ signature signature signature signature Table 16 Logano G315 – 6 720 817 939 (2017/02)
If the burner does not restart after three attempts, refer to the technical documentation provided with the burner to find out how to reset it. Logano G315 – 6 720 817 939 (2017/02)
Group 5 – jacket Group 6 – not available – Group 7 – not available – page 51 Group 8 – safety group Logano G315 Table 17 Spare part groups Logano G315 Logano G315 – 6 720 817 939 (2017/02)
Page 40
Spare parts 6720906566.aa.RS-Kesselblock G315 Fig. 68 Group 1 – boiler block - front Logano G315 Logano G315 – 6 720 817 939 (2017/02)
Page 42
Primer 181, 12.5 oz (370 ml) in 17 oz (500 ml) can Sealant graphite treated with linseed oil 450 g can Table 18 Group 1 – boiler block - front Logano G315 Logano G315 – 6 720 817 939 (2017/02)
Manufacturer no. ______________________ Location ______________________ The technical documentation has been handed over to the user. He has been familiarized with the safety instructions, operation and maintenance of the system. Date, signature (user) Logano G315 – 6 720 817 939 (2017/02)