PLATINUM Inverter 4300 TL, 4800 TL, 5300 TL, 6300 TL, 7200 TL
Mounting
Example
18
Installation and operating manual: PLATINUM Inverter 4300 TL, 4800 TL, 5300 TL, 6300 TL, 7200 TL
Version 05/2010
Mat. No. 734 559-AB
AC terminal
Destruction of the inverter due to high AC voltage!
Never connect the invterter between two phases.
Caution
Destruction of inverter due to high nominal alternating
power!
Observe the maximum admissible unbalanced load of
power plant operator.
Caution
Distribute inverters between the three phases in such
a way that the difference of alternating power on the
phases does not exceed the maximum admissible
unbalanced load.
In case of an unbalanced load of 4,600 W (nominal power) it is
possible to connect a PLATINUM inverter 5300 TL to a phase as a
single device. In case of a PLATINUM inverter 7200 TL, the nominal
AC power exceeds the admissible value. In this case, it is necessary
to divide the nominal AC power to at least two inverters with less
power and to at least two phases.