C.

Installing Heat Shield and Horizontal Termination Cap

WARNING
Fire Hazard
Impaired performance of appliance
• Telescoping ue section of termination
cap MUST be used when connecting pipe
section to termination cap.
• Maintain a 1-1/2 inch minimum overlap on
telescoping ue section of termination cap.
WARNING
Fire Risk
Exhaust Fumes Risk
Impaired Performance of Appliance
• Overlap pipe slip sections at least 1-1/2 inches.
• Use pilot holes for screws.
• Screws must not exceed 1 inch long.
• Pipe may separate if not properly joined.
Heat Shield Requirements for Horizontal Termination
For all horizontally vented appliances, a heat shield MUST
be placed one inch above the top of the vent between the
wall shield restop and the base of the termination cap.
There are two sections of the heat shield. One section
attaches to the wall shield restop with two screws. The
remaining section is attached to the cap in the same man-
ner.
If the wall thickness does not allow the required 1-1/2
inch heat shield overlap, an extended heat shield must
be used.
The extended heat shield will need to be cut to the thick-
ness of the wall and be attached to the wall shield restop.
The small leg on the extended heat shield should rest on
the top of the vent (pipe section) to properly space it from
the pipe section (see Figure 8.12).
Heat & Glo • SL-750TRS-IPI-D, SL-550TRS-IPI-D, SL350TRS-C • InD • 2065-985 Rev. o • 3/07
(DVP Pipe ONLY)
Installing the Horizontal Termination Cap
Vent termination must not be recessed in the wall. Siding
may be brought to the edge of the cap base.
Flash and seal as appropriate for siding material at outside
edges of cap.
When installing a horizontal termination cap, follow the cap
location guidelines as prescribed by current ANSI Z223.1
and CAN/CGA-B149 installation codes.
WARNING
Burn Risk
• Local codes may require installation of a
cap shield to prevent anything or anyone
from touching the hot cap.
Figure 8.13
Venting through the Wall
NOTE: Where required, an exterior wall ashing is
available.
When penetrating a brick wall, a brick extension kit
is available for framing the brick.