Using The Checklist; Table 4-2 Factory-Integrated Installation Checklist - HP 9000 rp7420 Installation Manual

Hp 9000 rp7420 server installation guide
Hide thumbs Also See for 9000 rp7420:
Table of Contents

Advertisement

Using the Checklist

The following checklist is an installation aid and should be used only after you have installed several systems
using the detailed procedures described in the body of this manual. This checklist is a compilation of the tasks
described in this manual, and is organized as follows:
PROCEDURES The procedures outlined in this document in order
IN-PROCESS
The portion of the checklist that allows you to comment on the current status of a procedure
COMPLETED
The final check to ensure that a step has been completed and comments
Major tasks are in bold type, sub tasks are indented.
Table 4-2
Factory-Integrated Installation Checklist
PROCEDURE
Obtain LAN information
Verify site preparation
Site grounding verified
Power requirements
verified
Check inventory
Inspect shipping containers
for damage
Unpack SPU cabinet
Allow proper clearance
Cut polystrap bands
Remove cardboard top cap
Remove cardboard wrap
from the pallet
Remove bolts holding down
the ramps and remove the
ramps
Remove antistatic bag
Check for damage (exterior
and interior)
Position ramps
Roll cabinet off ramp
Unpack the peripheral
cabinet (if ordered)
Chapter 4
IN-PROCESS
Initials
Comments
Cabling and Power Up
Using the Checklist
COMPLETED
Initials
Comments