1. Test Operation

1.1

Procedure and Outline

Follow the following procedure to conduct the initial test operation after installation.
1.1.1 Check work prior to turn power supply on
Check that the installation work for the indoor and outdoor units has been performed in accordance with the
instructions in the Installation Manual.
Check the below items.
• Power wiring
• Control transmission wiring
between units
• Earth wire
• Branch switch
• Earth leakage circuit breaker
Check on refrigerant piping /
insulation materials
Check air tight test and vacuum
drying.
Check on amount of additional
refrigerant charge
Check the stop valves for
conditions.

Test Operation

Is the wiring performed as specified?
Are the branch switches and earth leakage circuit breakers wired correctly?
Is the designated wire used?
Is the wiring screw of wiring not loose?
Is the grounding work completed?
Is the insulation of the main power supply circuit deteriorated?
Use a 500V megger tester to measure the insulation. (*1)
• Do not use a megger tester for other circuits than 400V or 200V circuit.
*1:Measure to be taken against decreased insulation resistance in the
compressor
If the compressor is left to stand for
an extended period of time after the
refrigerant charge with the stop
valve open and the power supply
OFF, the refrigerant may be mixed in
the compressor, thus decreasing the
insulation resistance.
Heat the compressor as shown on
the right and then recheck the
insulation.
Is the pipe size proper? Are the design pressures for the gas pipe and
liquid pipe more than 3.3MPa?
Is the pipe insulation material installed securely?
Liquid and gas pipes need to be insulated. (Otherwise causes water leak.)
Have the air tight test and the vacuum drying been conducted according to
the procedure in the Installation Manual?
Is a proper quantity of refrigerant charged?
* Refer to the following page for the calculation of the amount of
additionally refrigerant charge.
• When the refrigerant level is insufficient, leave the liquid and gas stop
valves closed and charge with liquid refrigerant via the liquid stop valve
service port. (* Do not charge via the gas stop valve service port. Doing
so will result in error.)
Is the amount of additional refrigerant charge recorded in the [Service
Precaution] label?
Check to be sure the stop valves are under the following conditions.
Liquid side
Model
stop valve
RQYQ8-48PY1B
Gas side
stop valve
Open
Open
Test Operation
Terminal
Dryer
(1000W)
61