section 113 Replacing the gas valve
A
DANGER OF FATAL ACCIDENT/FIRE
from explosive fumes.
All work on gas pipe work and fittings must be carried out
by authorized gas technicians.
While carrying out these activities check all sealing
rings and gaskets for damage, deformation and signs of
ageing and replace if required.
After carrying out these activities, check the system for
leaks on the gas side and/or the flue gas side.
After carrying out these activities check the measuring
nipples used for leaks using a foaming agent which has
been approved for gas leak testing.
Switch off the power supply to the heating system, see
section 72.
Open the boiler door and remove the casing of the pump
group as instructed in section 73.
Close the gas stop valve as indicated in section 74.
Disassemble the gas valve as indicated in section 86.
2
3
100 kW: Loosen the 4 torx screws [1] and remove the gas
valve [2] from the venturi pipe [3].
Install a new O-ring [1] in the venturi pipe.
Logamax plus GB162-80 kW/100 kW - Subject to modifications resulting from technical improvements!
1
1
1
Install the orifice [1] in the venturi pipe.
Install the new gas valve on the venturi pipe in reverse order,
as instructed before.
If necessary, replace the gasket between the fan unit and the
venturi pipe as instructed in section 86.
Install the new gas valve including the venturi pipe on the fan
unit in reverse order, as instructed before.
Check the rubber seal [1] for signs of ageing and damage and
replace it if necessary.
Install the gas/air unit including the burner cover in reverse
order of removal as instructed in section 86.
Install the air suction pipe on the venturi pipe in reverse order,
as instructed in section 86.
Connect the plug of the fan unit power supply cord and the
plug of the fan unit tacho cable in reverse order as instructed
in section 86.
Attach the gas valve plug or plugs in reverse order of removal
A
as instructed in section 86.
CAUTION!
While connecting the gas pipe to the gas valve make sure
that the rubber seal is fitted between the gas pipe and the
gas valve.
Connect the gas pipe to the gas valve in reverse order as
instructed in section 86.
Open the gas stop valve as indicated in section 81.
Switch on the power supply to the heating system, see
section 79.
Check the gas/air ratio and adjust it if necesaary, see
section 119.
Close the boiler door as instructed in section 91.