Vent Installation - Travis Industries DVL EF Owner's Manual

Table of Contents

Advertisement

Installation

Vent Installation

In addition to the requirements below, follow the requirements provided with the vent.
Vertical Vent
Requirements
Use a roof flashing and storm collar
whenever passing through the roof
Use a firestop whenever passing through a
ceiling (or enclosure and at every floor
penetration.
Horizontal Vent
Requirements
Slide the vent sections together and turn 1/4 turn until the sections lock in
place.
Screws are not required to secure the vent. However, three screws may be
used to secure vent sections together if desired.
High temperature sealant is recommended at the appliance starter section
connection (use high-temperature silicone or Mill-Pac®).
If disassembly is required, at time of re-assembly check to see if the vent
creates a tight fit. If it does not, apply high temperature sealant to the joints of
the affected sections.
Horizontal sections require a 1/4" rise every 12" of travel
Horizontal sections require non-combustible support every three feet (e.g.: plumbing tape)
Travis Industries
(for qualified installers only)
Use the Travis Firestop (part # 93006094) when passing through a
wall. NOTE: make sure the firestop is postitioned correctly so the 3"
clearance is allowed above the vent.
4041206
Vertical Termination
(part # 1291)
Combustible
Framing
Min. 1" Clearance on
Vertical Sections to
combustible surfaces.
1" Min.
Combustible
Surfaces
3" Min.
1" Min.
1 0 0 - 0 1 1 4 7
1 9

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents