14

E1/T1 Installation Guide

14.1

Preparing the PTP 600 Series Bridge E1/T1 Cable

Note: The maximum cable length between the ODU and the customers terminating
equipment is 200m (656 feet) for T1.
The E1/T1 cable should be assembled to the following instructions:
Step 1: Assemble gland on cable as shown
Step 3: Arrange conductors as shown in fig.
A2 and cut to length

Figure 111 - Completed ODU Connector

195
Step 2: Strip the outer insulation
Step 4: Insert conductors and crimp