Initial operation
4
Initial operation
4.1 Switch on
4.2 Initial operation
▪ To transfer all settings correctly, initial operation must be conducted
in full once.
▪ When installing several inverters that are linked with each other via
the PLATINUM® network (EIA485), initial operation can be performed
on any inverter (master programming). For this to be possible, all
inverters in the network must be switched on.
▪ The inverter automatically transfers the setting values to the other
inverters via the PLATINUM® network (EIA485).
▪ Every inverter is allocated a number automatically during initial
operation. This number can be changed and freely assigned in a
further step.
▪ The inverters on which no data is entered display different screen
content depending on the menu. If data cannot be entered, the
inverter displays the start screen.
▪ During initial operation, all inverters connected to the PLATINUM®
network are blocked.
20
1. Switch on mains voltage supply (safety).
2. Switch on DC voltage via the DC isolator on the
left side of the inverter.
The inverter type appears in the display along
with the prompt START?.
Installation and user guide PLATINUM® Inverter 7000 R3, 9000 R3, 11000 R3, 14000 R3, 16000 R3