4
Placing into operation
4.1 Switch on
4.2 Initial operation
▪ To transfer all settings correctly, initial operation must be conducted in
full once.
▪ When installing several inverters that are linked with each other via the
PLATINUM® network (eIA485), initial operation can be performed on
any inverter (master programming). for this to be possible, all inverters
in the network must be switched on.
▪ The inverter automatically transfers the setting values to the other
inverters via the PLATINUM® network (eIA485).
▪ every inverter is allocated a number automatically during initial
operation. This number can be changed and freely assigned in a further
step.
▪ The inverters on which no data is entered display different screen
content depending on the menu. If data cannot be entered, the
inverter displays the start screen.
▪ During initial operation, all inverters connected to the
PLATINUM®network are blocked.
Installation and user guide for inverter PLATINUM® 13000 TL, 16000 TL, 19000 TL, 22000 TL, 22001 TL
1. Switch on mains voltage supply (safety device).
2. Switch on the DC voltage via the 3 DC
disconnects on the underside of the device or via
the external isolation device.
The inverter type appears on the display along
with the prompt STArT?.
Placing into operation
27