EdilKamin Installation Clearances & Specifications

Installation Clearances

Minimum clearances shown are in mm, and all figures for
clearances are to combustible materials. All EdilKamin pellet
fires are tested using all applicable procedures and equipment
under AS/NzS2918:2001.
Rear Clearance Options
The 100mm rear clearance measurement "4" is based on the
EdilKamin pellet fire having the vent system penetrating the
rear wall behind the pellet fire and is the minimum clearances
required for this type of installation.
Please Note: If the vent system is going to be visible in the room and exit
through the ceiling, a minimum clearance of 80mm is required from the rear
surface of the vent system to a combustible wall. A 250mm rear clearance
is therefore recommended. Also consider the thickness of the scotia as this
will determine how close the vent can be to the wall.
Optional Direct Vent Combustion Air Supply
The EdilKamin pellet fires have a direct vent option which
when installed draws the combustion air from outside the
home, further improving the efficiency of the pellet fire. This is
Model Clearances
EdilKamin Iris Plus
EdilKamin Little
*Please Note: Measurement 4 details the vent system using a wall or ceiling kit. 100mm = Vent through wall, 250mm = Vent through ceiling.
EdilKamin Iris Plus
EdilKamin Little
1
200mm
8
800mm
IRIS PLUS
6
2
3
106mm 77
215mm
600mm
IRIS PLUS (REAR PROFILE)
1
2
200
77
200
77
600
950
480
940
4
100/250mm*
1
200mm
530mm
5
200mm
6
7
recommended as the Iris Plus and Little pellet fires can use up
to 24 cubic metres of room air every hour.
There are three methods of supplying the pellet fire with
combustion air. They are as follows;
• DV WALL KIT ducts through an outside wall
• DV FLOOR KIT ducts through the floor directly behind the fire
• DV CEILINg KIT ducts into the wall and up into the ceiling
cavity
If using a thru wall exhaust vent in combination with a DV
air intake kit, be sure to offset the DV air hole approximately
50mm to allow for the external flashings, this will vary
depending on type of kit used.
Warranty
Your EdilKamin Pellet fire is covered by a full 12 month
warranty, and a three year firebox warranty. This warranty is
subject to the unit being operated and maintained as detailed
in the operation manual.
3
4
5
106
100/250*
200
106
100/250*
200
530
140kg
470
136kg
4
100/250mm*
490mm
5
200mm
8
680mm
LITTLE
7
3
2
134mm 106
160mm
480mm
LITTLE (REAR PROFILE)
PAGE 9
6
7
320
375
315
370
8kW
Yes
0.61
5kW
Yes
0.38
160mm
5
950mm
IRIS PLUS/LITTLE
CORNER INSTALLATION
8
9
800
160
680
160
70.6%
73.8%