Installation and Operation Manual (REV H)
Neutral
208
240
Neutral
120
240
2.4 Connection of the AC wiring
Use one of the following procedures below to wire the AC conductors.
Open the circuit breaker box, switch off and lock out the circuit breaker box that will be used to connect the inverter to the
building.
WARNING!
Reconfirm that the circuit breaker to the grid/utility is switched OFF and locked out before connecting the power
wires from the breaker to the inverter AC terminal block. Measure the absence of voltage with an AC voltmeter.
WARNING!
!
Long wires cause voltage drop. The acceptable range for AC voltage drop is 1.5% of nominal. The voltage drop in
excess of 1.5% of nominal AC voltage is an indication that larger size wire should be used.
With Neutral
120 WYE
120
With Neutral
240 Delta
120 Stinger
P1
P2
Without Neutral
240 Delta
Fig 2.3.8 Utility configurations
With Neutral
240/120 Split Phase
120
120
Neutral
240
With Neutral
277 WYE
480
208
Without Neutral
24
PVI 6500 / PVI 7500
P1
P2
277V / 240V / 208V
With Neutral
P1
P2
208 Delta