UPS ELECTRICAL INSTALLATION
44
+
Eaton 9170
UPS (3–18 kVA) User's Guide
3.
Install the conduit adapters. AC input and AC output conductors
must be run through separate conduits. UPS output circuits must
be installed in dedicated conduit systems and not shared with other
electrical circuits.
Figure 27 shows input and output wiring terminals inside the Eaton
9170+ UPS cabinet.
Backplane Board
Terminating
Studs
Figure 27. UPS Input and Output Terminals
4.
Torque the screws holding all input and output power conductors to
the values specified in Table 7 on page 41.
S
164201393 Rev E www.eaton.com/powerquality
+DC
X3
X2
X1
X2
+DC
X1
3
2
1
N
-DC
N
-DC