Installing the system unit in the rack

V
CAUTION!
For safety reasons, at least three people are needed to install the
system unit in the rack because of its weight and size.
Please observe the safety information and notes on rack installation
in the
chapter "Important notes"
The rack can tip over if more than one unit is pulled out.
Rack requirements
The rack systems from Fujitsu PRIMECENTER Rack, DataCenter Rack and
19-inch standard rack (for the Japanese market) support the installation of
PRIMERGY servers. Installation in most current rack systems from other
manufacturers (3rd party racks) is also supported.
To accommodate the ventilation concept and ensure proper ventilation, any
unused areas in the rack must be sealed using dummy covers.
The mains connection is implemented via external distributors, a suitable power
distribution unit or a UPS device.
PRIMECENTER/DataCenter Rack
The individual rack systems from Fujitsu Technology Solutions have the
following features:
– Rails that are screwed on at the front.
The length of the rails can be adjusted to allow different rack depths.
– Enhanced cable management in the lateral rack area.
I
For PRIMECENTER Racks and DataCenter Racks:
The mounting of the rails in the different racks is described in the next
sections. Installation of the cable management is described in detail in
the Technical Manual for the respective rack.
I
For 19-inch standard rack (for the Japanese market):
For information on mounting of the rails in the 19-inch standard rack (for
the Japanese market) please refer to the "Rack mount guide".
For rack systems from other manufacturers:
BX900 S1
as of
Operating Manual
Installing the hardware
page
36.
41

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents