Site Preparation Guidelines

Site Planning Time Table

Site Planning Time Table
The guidelines below are a summary of the Pre-Installation Worksheet
in Appendix A of this manual. The worksheet should be used to monitor
the progress of pre-installation preparation. Since the time from placing
an order to actual delivery may vary, it is suggested that you confer with
your Hewlett-Packard CE and Sales Representative, your electrician,
and others to determine the best estimated delivery dates for the
preparation of your site.
The following are four items that may require several weeks lead time:
• Arranging for an electrician
• Adding air conditioning
• Building alterations
• Placing orders for data communications equipment
Due to potential delays, Hewlett-Packard recommends that the suppliers
of the above services be contacted as soon as possible after your computer
system has been ordered.
There are four items that may require up to six weeks lead time:
• Assigning your Principal Operator.
• When your purchase order has included the optional site planning
visit, scheduling this visit with the Hewlett-Packard CE to answer
your questions about site preparation.
• Selecting an appropriate system location and planning the physical
arrangement of the system, including any related furniture.
• Ordering any consumable supplies, including any appropriate storage
media (such as DDS tapes or floppy diskettes).
To schedule the site planning visit, three days advance notice is required.