Table 1-1
Introduction
Hewlett-Packard Service Organization
Site Preparation Technical Tasks
Technical Tasks
Line voltage measured
Power line frequency measured (if required)
Power line noise levels measured (if required)
Neutral or ground noise/voltage levels measured
Safety and ground connections verified
Advice on correct circuit breakers and wire size
Verification that maintenance power outlets
(those used for floor cleaning, etc.) are on
separate circuits from the computer system
Recommendations about lightning protection
Measurements and recommendations on
radiated interference
Answers to questions concerning modems and
modem options
Thermal load of HP equipment
Thermal load of non-HP equipment
Modifications to existing electrical service
Modifications to existing air conditioning
Environmental contaminants
Placement of equipment (for service access)
6
Responsible Personnel
Electrician and Customer
Engineer (CE)
CE
CE
CE
Electrician and CE
Electrician and CE
Electrician and CE
CE
CE
Applications Engineer (AE)
CE
Customer and Equipment
Vendor
Electrician and Customer
A/C Contractor and Customer
CE and Environmental
Engineer/Contractor
CE