3-1. Table processing diagram

• The thickness of the table should be at least 40 mm, and it should be strong enough to bear the weight and vibration of the
sewing machine.
• If the distance A between the insides of the legs is less than 740 mm, move the control box installation position to the left (B =
261mm).
• Check that the control box is at least 10 mm away from the leg. If the control box and the leg are too close together, it may result
in incorrect sewing machine operation.
<For BAS-311G and 326G>
<For BAS-300G>
Only the holes for installing the operation panel and
the hole for the cord differ from the above diagram.
Refer to the diagram above for all other dimensions.
* The operation panel can be moved to any
preferred position as long as it is in a position
where the cord reaches the PCB inside the
control box.
BAS-300G, BAS-311G, BAS-326G
3. INSTALLATION
3000B
(Reference position)
3003B
4

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Bas-311gBas-326g

Table of Contents