Page 1
E E a a t t o o n n ® 9 9 3 3 9 9 0 0 U U P P S S S S i i d d e e c c a a r r 40–80 kVA Installation and Operation Manual For use with 40–80 kVA and 100–160 kVA UPS Models p/n: 164201586...
Page 3
Dear Customer, On behalf of everyone at Eaton, we thank you for partnering with us, for trusting us to maintain your business continuity and for preventing downtime at your facility. Our suite of backup power, power distribution and power management products are designed to protect you from a host...
Page 4
2 2 . . 2 2 L L i i c c e e n n s s e e G G r r a a n n t t . Eaton grants to Licensee a limited, revocable, non-exclusive, non-assignable...
Page 5
5 5 . . 1 1 U U p p d d a a t t e e P P o o l l i i c c y y .
Page 6
Third Party Licensors contained in the Firmware. 5 5 . . 1 1 1 1 I I n n d d e e m m n n i i t t y y . Licensee shall defend, indemnify and hold Eaton and its officers, directors, employees, and agents harmless from and against all losses, damages, liabilities, claims, actions, and associated costs and expenses (including reasonable attorneys’...
Page 7
5 5 . . 1 1 2 2 O O p p e e n n S S o o u u r r c c e e S S o o f f t t w w a a r r e e .
Page 10
5 5 I I n n s s t t a a l l l l a a t t i i o o n n I I n n f f o o r r m m a a t t i i o o n n ....................................................3 3 5 5 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 11
120, and 160/160 kVA, 480/480V with MOBs and Optional SLB ............. 31 Figure 18. 164201586-1 Typical Eaton 9390 UPS System with UPS Sidecar (Sheet 1) ..........36 Figure 19. 164201586-1 Typical Eaton 9390 UPS System with UPS Sidecar (Sheet 2) ..........37 Figure 20.
Page 12
164201586-6 Power Terminal Locations (Sheet 28) ................91 Figure 74. 164201586-6 Power Terminal Locations (Sheet 29) ................92 Figure 75. 164201586-6 Power Terminal Locations (Sheet 30) ................93 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
List of Figures EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 15
The Eaton ® 9390 UPS Sidecar is designed for use with the Eaton 9390 80 kVA 208/208V and 480/480V and 160 kVA 480/480V three-phase uninterruptible power systems (UPSs). The UPS Sidecar provides maintenance bypass or tie cabinet functions with the following custom configurable features, enabling adaptation and expansion without costly electrical rework: •...
Page 16
F F i i g g u u r r e e 2 2 . . E E a a t t o o n n 9 9 3 3 9 9 0 0 U U P P S S ( ( 1 1 0 0 0 0 – – 1 1 6 6 0 0 k k V V A A ) ) w w i i t t h h U U P P S S S S i i d d e e c c a a r r EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 17
U U s s i i n n g g T T h h i i s s M M a a n n u u a a l l This manual describes how to install and operate the Eaton 9390 UPS Sidecar. Read and understand the procedures described in this manual to ensure trouble-free installation and operation.
Page 18
The operating environment should be maintained within the parameters stated in this manual. Keep surroundings uncluttered, clean, and free from excess moisture. • Observe all DANGER, CAUTION, and WARNING notices affixed to the inside and outside of the equipment. EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Phillips and Pozidriv are registered trademarks of Phillips Screw Company. Eaton, Powerware, and BladeUPS are registered trademarks of Eaton Corporation or its subsidiaries and affiliates. ECopyright 2008–2010 Eaton Corporation, Raleigh, NC, USA. All rights reserved. No part of this document may be •...
Page 20
W W a a r r r r a a n n t t y y a a n n d d E E n n d d U U s s e e r r L L i i c c e e n n s s e e A A g g r r e e e e m m e e n n t t To view the warranty please click on the link or copy the address to download from the Eaton website: Eaton Product Warranty https://www.eaton.com/content/dam/eaton/products/backup-power-ups-surge-it-power-distribution/backup-...
N N O O T T E E Wire grounds to the ground terminals located inside the UPS cabinet. Verify the UPS system is turned off and all power sources are removed. Refer to the applicable Eaton 9390 installation and operation manual, listed in 1.6 For More...
15. When all wiring is complete, reinstall the internal safety shield panels removed in previous steps. 16. Reinstall the UPS Sidecar front panel and secure with the screw at the bottom of the panel. EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 23
To install a line-up-and-match parallel redundant system, continue to 2.4.1 Line-up-and-Match Parallel Redundant Installation. • To install a standalone parallel redundant system, proceed to 2.4.3 Standalone Parallel Redundant Installation. EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 24
F F i i g g u u r r e e 4 4 . . T T y y p p i i c c a a l l L L i i n n e e - - u u p p - - a a n n d d - - M M a a t t c c h h P P a a r r a a l l l l e e l l R R e e d d u u n n d d a a n n t t S S y y s s t t e e m m ( ( 8 8 0 0 k k V V A A S S y y s s t t e e m m S S h h o o w w n n ) ) Sidecar Verify that the UPM 1 is properly installed and secured. Refer to the applicable Eaton 9390 installation and operation manual, listed in 1.6 For More...
Page 25
Figure 45). Remove the knockouts on the bottom left side inside panel of UPM 2. Refer to the applicable Eaton 9390 installation and operation manual, listed in 1.6 For More Information, for the location of the knockout plug.
Page 26
Specified wiring and the MOB and SLB breakers for the UPS Sidecar are rated for parallel redundant service only. DO NOT use as a parallel capacity system. Verify the UPS system is turned off and all power sources are removed. Refer to the applicable Eaton 9390 installation and operation manual, listed in 1.6 For More...
Page 27
Use this procedure to install separately located UPMs (see Figure 6). UPM 1 has the Sidecar installed. The UPS Sidecar is a factory-installed integral part of the standard UPS cabinet. EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 28
F F i i g g u u r r e e 6 6 . . T T y y p p i i c c a a l l S S t t a a n n d d a a l l o o n n e e P P a a r r a a l l l l e e l l R R e e d d u u n n d d a a n n t t S S y y s s t t e e m m ( ( 8 8 0 0 k k V V A A S S y y s s t t e e m m S S h h o o w w n n ) ) UPS Sidecar Verify that the UPM 1 is properly installed and secured. Refer to the applicable Eaton 9390 installation and operation manual, listed in 1.6 For More...
Page 29
Information. Correct wire length ensures approximate equal current sharing when in Static Bypass mode. Verify the UPS system is turned off and all power sources are removed. Refer to the applicable Eaton 9390 installation and operation manual, listed in 1.6 For More Information, for shutdown instructions.
Page 30
I I n n i i t t i i a a l l S S t t a a r r t t u u p p Startup and operational checks must be performed by an authorized Eaton Customer Service Engineer, or the warranty terms specified in 1.8 Warranty and End User License...
Page 31
Installing the UPS Sidecar N N o o t t e e s s _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 32
Installing the UPS Sidecar EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 33
UPS through the MIS. The MIS is then opened, isolating the UPS from the Bypass power source. The UPS can be safely shut down and power removed from the UPS without interrupting power to the critical load. If the EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 34
P P a a r r a a l l l l e e l l R R e e d d u u n n d d a a n n t t C C o o n n f f i i g g u u r r a a t t i i o o n n Refer to the applicable Eaton 9390 installation and operation manual, listed in paragraph 1.5 1.6 For More...
Page 35
U U P P S S S S i i d d e e c c a a r r C C o o n n t t r r o o l l s s Figure 9 through Figure 16 identify and show the location of the controls on the Eaton 9390 UPS Sidecar. EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
UPS Sidecar Features, Controls, and Operation N N O O T T E E Read the operation sections of this manual and the applicable Eaton 9390 installation and operation manual, listed in 1.6 For More Information, and have thorough knowledge of UPS operation before attempting to operate any of the UPS Sidecar controls.
Page 37
F F i i g g u u r r e e 9 9 . . U U P P S S S S i i d d e e c c a a r r C C o o n n t t r r o o l l s s ( ( B B y y p p a a s s s s ) ) – – 4 4 0 0 / / 2 2 0 0 , , 4 4 0 0 / / 3 3 0 0 , , 4 4 0 0 / / 4 4 0 0 k k V V A A , , 4 4 8 8 0 0 / / 4 4 8 8 0 0 V V w w i i t t h h M M B B P P a a n n d d M M I I S S Interlock Plate Maintenance Isolation Maintenance Bypass Switch (MIS) Switch (MBP) EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 38
F F i i g g u u r r e e 1 1 0 0 . . U U P P S S S S i i d d e e c c a a r r C C o o n n t t r r o o l l s s ( ( B B y y p p a a s s s s ) ) – – 4 4 0 0 / / 2 2 0 0 , , 4 4 0 0 / / 3 3 0 0 , , 4 4 0 0 / / 4 4 0 0 k k V V A A , , 4 4 8 8 0 0 / / 4 4 8 8 0 0 V V w w i i t t h h O O p p t t i i o o n n a a l l B B I I B B a a n n d d R R I I B B Optional Rectifier Input Breaker (RIB) Optional Bypass Input Breaker (BIB) Interlock Plate Maintenance Isolation Maintenance Bypass Switch (MIS) Switch (MBP) EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 39
8 8 0 0 / / 8 8 0 0 k k V V A A a a n n d d 1 1 2 2 0 0 / / 1 1 0 0 0 0 a a n n d d 1 1 2 2 0 0 / / 1 1 2 2 0 0 k k V V A A , , 4 4 8 8 0 0 / / 4 4 8 8 0 0 V V w w i i t t h h M M B B P P a a n n d d M M I I S S Maintenance Bypass Switch (MBP) Interlock Plate Maintenance Isolation Switch (MIS) EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 40
8 8 0 0 / / 8 8 0 0 k k V V A A a a n n d d 1 1 2 2 0 0 / / 1 1 0 0 0 0 a a n n d d 1 1 2 2 0 0 / / 1 1 2 2 0 0 k k V V A A , , 4 4 8 8 0 0 / / 4 4 8 8 0 0 V V w w i i t t h h O O p p t t i i o o n n a a l l B B I I B B a a n n d d R R I I B B Optional Rectifier Input Breaker (RIB) Optional Bypass Input Breaker (BIB) Maintenance Bypass Switch (MBP) Interlock Plate Maintenance Isolation Switch (MIS) EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 41
1 1 6 6 0 0 / / 1 1 2 2 0 0 , , a a n n d d 1 1 6 6 0 0 / / 1 1 6 6 0 0 k k V V A A , , 4 4 8 8 0 0 / / 4 4 8 8 0 0 V V w w i i t t h h M M B B P P a a n n d d M M I I S S Maintenance Bypass Switch (MBP) Maintenance Isolation Switch (MIS) EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 42
1 1 6 6 0 0 / / 1 1 2 2 0 0 , , a a n n d d 1 1 6 6 0 0 / / 1 1 6 6 0 0 k k V V A A , , 4 4 8 8 0 0 / / 4 4 8 8 0 0 V V w w i i t t h h O O p p t t i i o o n n a a l l B B I I B B a a n n d d R R I I B B Optional Rectifier Input Breaker (RIB) Optional Bypass Input Breaker (BIB) Maintenance Bypass Switch (MBP) Maintenance Isolation Switch (MIS) EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 43
O O p p t t i i o o n n a a l l S S L L B B Optional System Load Breaker (SLB) Module Output Breaker 1 Module Output Breaker 2 (MOB 1) (MOB 2) EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 44
8 8 0 0 / / 5 5 0 0 , , 8 8 0 0 / / 6 6 0 0 , , 8 8 0 0 / / 8 8 0 0 k k V V A A a a n n d d 1 1 2 2 0 0 / / 1 1 0 0 0 0 , , a a n n d d 1 1 2 2 0 0 / / 1 1 2 2 0 0 k k V V A A , , 4 4 8 8 0 0 / / 4 4 8 8 0 0 V V w w i i t t h h M M O O B B s s a a n n d d O O p p t t i i o o n n a a l l S S L L B B Optional System Load Breaker (SLB) Module Output Breaker 1 (MOB 1) Module Output Breaker 2 (MOB 2) EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 45
1 1 6 6 0 0 / / 1 1 0 0 0 0 , , 1 1 6 6 0 0 / / 1 1 2 2 0 0 , , a a n n d d 1 1 6 6 0 0 / / 1 1 6 6 0 0 k k V V A A , , 4 4 8 8 0 0 / / 4 4 8 8 0 0 V V w w i i t t h h M M O O B B s s a a n n d d O O p p t t i i o o n n a a l l S S L L B B Optional System Load Breaker (SLB) Module Output Breaker 1 (MOB 1) Module Output Breaker 2 (MOB 2) EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 46
Reinstall the UPS Sidecar front panel and secure with the screw at the bottom of the panel. Start the UPS in Normal mode according to the instructions in the operation chapter of the applicable Eaton 9390 installation and operation manual, listed in 1.6 For More...
Page 47
Remove the screw securing the bottom of the UPS Sidecar front panel. Lift up the panel and remove. Close the BIB and RIB, if installed. Verify that the UPS is operating and is in Bypass mode. Refer to the applicable Eaton 9390 installation and operation manual, listed in 1.6 For More...
Page 48
M M a a i i n n t t a a i i n n i i n n g g t t h h e e U U P P S S S S i i d d e e c c a a r r The UPS Sidecar maintenance is the same as the UPS. Refer to the applicable Eaton 9390 installation and operation manual, listed in paragraph 1.6 For More...
Page 49
• 164201586-5 Conduit and Wire Entry Locations • 164201586-6 Power Terminal Locations • 164201586-7 Interface and Control Wiring Installation Notes and Terminal Locations • 164201586-8 UPS Sidecar Dimensions EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
80 kVA UPS CABINET TYPICAL MAINTENANCE BYPASS OR STANDALONE PARALLEL REDUNDANT CONFIGURATION DESCRIPTION: TYPICAL EATON 9390 UPS SYSTEM WITH UPS SIDECAR DRAWING NO 164201586-1 1 of 3 REVISION: DATE: 031505 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 51
160 kVA UPS CABINET TYPICAL MAINTENANCE BYPASS OR STANDALONE PARALLEL REDUNDANT CONFIGURATION DESCRIPTION: TYPICAL EATON 9390 UPS SYSTEM WITH UPS SIDECAR DRAWING NO 164201586-1 2 of 3 REVISION: DATE: 031505 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 52
CABINET 2 TYPICAL LINE UP AND MATCH PARALLEL REDUNDANT CONFIGURATION DESCRIPTION: TYPICAL EATON 9390 UPS SYSTEM WITH UPS SIDECAR DRAWING NO 164201586-1 3 of 3 REVISION: DATE: 031505 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 53
F F i i g g u u r r e e 2 2 1 1 . . 1 1 6 6 4 4 2 2 0 0 1 1 5 5 8 8 6 6 - - 2 2 P P h h y y s s i i c c a a l l F F e e a a t t u u r r e e s s a a n n d d R R e e q q u u i i r r e e m m e e n n t t s s ( ( S S h h e e e e t t 1 1 ) ) The UPS Sidecar equipment operating environment must meet the weight requirements shown in the applicable Eaton 9390 installation and operation manual, listed in paragraph 1.5, plus 150 pounds for the UPS Sidecar. Size requirements are shown in Drawing 164201586-8 starting on page A-68.
Page 54
2. Remove jumper for dual feed. DRAWING NO 164201586-3 1 of 11 3. If the load requires a neutral, a bypass REVISION: DATE: neutral feeder must be supplied. 033108 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 55
2. Remove jumper for dual feed. DRAWING NO 164201586-3 3. If the load requires a neutral, a bypass 2 of 11 neutral feeder must be supplied. REVISION: DATE: 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 56
2. Remove jumper for dual feed. DRAWING NO 164201586-3 3 of 11 3. If the load requires a neutral, a bypass REVISION: DATE: neutral feeder must be supplied. 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 57
DRAWING NO 164201586-3 4 of 11 3. If the load requires a neutral, a bypass REVISION: DATE: neutral feeder must be supplied. 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 58
1. Remove jumper for dual feed. DESCRIPTION: UPS SIDECAR ONELINE DRAWINGS 2. If the load requires a neutral, a bypass DRAWING NO neutral feeder must be supplied. REVISION: DATE: 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 59
1. Remove jumper for dual feed. DESCRIPTION: UPS SIDECAR ONELINE DRAWINGS 2. If the load requires a neutral, a bypass DRAWING NO neutral feeder must be supplied. REVISION: DATE: 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 60
1. Remove jumper for dual feed. DESCRIPTION: UPS ONLINE ONELINE DRAWINGS 2. If the load requires a neutral, a bypass DRAWING NO neutral feeder must be supplied. REVISION: DATE: 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 61
UPS SIDECAR ONELINE DRAWINGS 2. If the load requires a neutral, a bypass DRAWING NO neutral feeder must be supplied. REVISION: DATE: 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 62
DESCRIPTION: UPS SIDECAR ONELINE DRAWINGS 2. If the load requires a neutral, a bypass neutral feeder must be supplied. DRAWING NO 164201586-3 9 of 11 REVISION: DATE: 033108 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 63
DESCRIPTION: UPS SIDECAR ONELINE DRAWINGS 3. If the load requires a neutral, a bypass neutral feeder must be supplied. DRAWING NO 164201586-3 10 of 11 REVISION: DATE: 033108 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 64
2. Remove jumper for dual feed. DRAWING NO 3. If the load requires a neutral, a bypass 164201586-3 11 of 11 neutral feeder must be supplied. REVISION: DATE: 031505 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 65
164201586-3, sheets 1 of 9, 5 of 9, and 9 of 9. DESCRIPTION: POWER WIRING INSTALLATION NOTES DRAWING NO 164201586-4 1 of 10 REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 66
3 of 9, 4 of 9, 5 of 9, 6 of 9, 7 of 9, 8 of 9, and 9 of 9. DESCRIPTION: POWER WIRING INSTALLATION NOTES DRAWING NO REVISION: DATE: 061507 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 67
For customer supplied wiring in a standalone installation, refer to the applicable Module Eaton 9390 installation and operation manual, listed in paragraph 1.5, for wire size. Number per Phase for each Module Wiring for line up and match installation is factory supplied.
Page 68
UPS and Sidecar. Refer to Section I of this manual for installation instructions. Refer to the applicable Eaton 9390 installation and operation manual, listed in paragraph 1.5, for UPS cabinet wiring requirements, and conduit and terminal locations.
Page 69
56.5 (500) 1/2” Hex Phase C 1 - #6-500 kcmil 56.5 (500) 1/2” Hex DESCRIPTION: POWER WIRING INSTALLATION NOTES DRAWING NO 164201586-4 5 of 10 REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 71
Refer to Table B through Table E for wiring requirements. DESCRIPTION: POWER WIRING INSTALLATION NOTES DRAWING NO 164201586-4 7 of 10 REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 73
Table O in accordance with the NEC, ANSI/NFPA 70. DESCRIPTION: POWER WIRING INSTALLATION NOTES DRAWING NO 164201586-4 9 of 10 REVISION: DATE: 062206 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
WIRES BETWEEN CABINETS. (INSTALL NYLON GROMMET AFTER REMOVAL OF KNOCKOUTS.) RIGHT SIDE VIEW DESCRIPTION: CONDUIT AND WIRE ENTRY LOCATIONS DRAWING NO 164201586-5 3 of 3 REVISION: DATE: 031505 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 78
MAINTENANCE BYPASS CONFIGURATION WITH BIB OPTION DESCRIPTION: POWER TERMINAL LOCATIONS NOTE Metal shields covering wiring terminals DRAWING NO 1 of 34 164201586-6 must be removed to gain access to REVISION: DATE: terminals. 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 79
MAINTENANCE BYPASS CONFIGURATION WITH BIB AND RIB OPTIONS DESCRIPTION: POWER TERMINAL LOCATIONS NOTE Metal shields covering wiring terminals DRAWING NO must be removed to gain access to terminals. REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 80
NOTE 1. Metal shields covering wiring DESCRIPTION: POWER TERMINAL LOCATIONS terminals must be removed to DRAWING NO 164201586-6 3 of 34 access terminals. 2. 80/40 must be wired as 80/50. REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 81
MAINTENANCE BYPASS CONFIGURATION NOTE Metal shields covering wiring DESCRIPTION: POWER TERMINAL LOCATIONS terminals must be removed to DRAWING NO 164201586-6 4 of 34 access terminals. REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 82
NOTE 1. Metal shields covering wiring DESCRIPTION: POWER TERMINAL LOCATIONS terminals must be removed to DRAWING NO 164201586-6 5 of 34 access terminals. 2. 80/40 must be wired as 80/50. REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 83
MAINTENANCE BYPASS CONFIGURATION WITH OPTIONAL BIB NOTE Metal shields covering wiring DESCRIPTION: POWER TERMINAL LOCATIONS terminals must be removed to DRAWING NO 164201586-6 6 of 34 access terminals. REVISION: DATE: 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 84
NOTE 1. Metal shields covering wiring DESCRIPTION: POWER TERMINAL LOCATIONS terminals must be removed to DRAWING NO 164201586-6 7 of 34 access terminals. 2. 80/40 must be wired as 80/50. REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 85
MAINTENANCE BYPASS CONFIGURATION WITH BIB AND RIB OPTIONS NOTE Metal shields covering wiring DESCRIPTION: POWER TERMINAL LOCATIONS terminals must be removed to DRAWING NO 164201586-6 8 of 34 access terminals. REVISION: DATE: 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
DRAWING NO 164201586-6 9 of 34 2. 80/40 must be wired as 80/50. REVISION: DATE: 3. 160/100 must be wired as 160/120. 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 87
DRAWING NO 164201586-6 10 of 34 2. 80/40 must be wired as 80/50. REVISION: DATE: 3. 160/100 must be wired a 160/120. 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
PARALLEL REDUNDANT CONFIGURATION DESCRIPTION: POWER TERMINAL LOCATIONS NOTE Metal shields covering wiring terminals DRAWING NO 164201586-6 11 of 34 must be removed to access terminals. REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 89
PARALLEL REDUNDANT CONFIGURATION WITH SLB DESCRIPTION: POWER TERMINAL LOCATIONS NOTE Metal shields covering wiring terminals DRAWING NO must be removed to access terminals. 164201586-6 12 of 34 REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 90
40/20, 40/30, 40/40 KVA, 208/208V PARALLEL REDUNDANT CONFIGURATION DESCRIPTION: POWER TERMINAL LOCATIONS NOTE Metal shields covering wiring terminals DRAWING NO must be removed to access terminals. REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 91
80/40, 80/50, 80/60, 80/80 KVA, 480/480V PARALLEL REDUNDANT CONFIGURATION DESCRIPTION: POWER TERMINAL LOCATIONS NOTE Metal shields covering wiring terminals DRAWING NO must be removed to access terminals. REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 92
120/100, 120/120 KVA, 480/480V PARALLEL REDUNDANT CONFIGURATION DESCRIPTION: POWER TERMINAL LOCATIONS NOTE Metal shields covering wiring terminals DRAWING NO must be removed to access terminals. REVISION: DATE: 063006 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 93
NOTE 1. Metal shields covering wiring POWER TERMINAL LOCATIONS terminals must be removed to DRAWING NO 164201586-6 16 of 34 access terminals. 2. 80/40 must be wired as 80/50. REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 94
NOTE 1. Metal shields covering wiring POWER TERMINAL LOCATIONS terminals must be removed to DRAWING NO 164201586-6 17 of 34 access terminals. 2. 80/40 must be wired as 80/50. REVISION: DATE: 061507 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 95
NOTE 1. Metal shields covering wiring POWER TERMINAL LOCATIONS terminals must be removed to DRAWING NO 164201586-6 18 of 34 access terminals. 2. 80/40 must be wired as 80/50. REVISION: DATE: 063006 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 96
DRAWING NO 164201586-6 19 of 34 2. 80/40 must be wired as 80/50. REVISION: DATE: 3. 160/100 must be wired as 160/120. 063006 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 97
DRAWING NO 164201586-6 20 of 34 2. 80/40 must be wired as 80/50. REVISION: DATE: 3. 160/100 must be wired as 160/120. 063006 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 98
AC OUTPUT TERMINAL BLOCK PHASE A AC OUTPUT PHASE B TO CRITICAL LOAD PHASE C DESCRIPTION: POWER TERMINAL LOCATIONS DRAWING NO 21 of 34 164201586-6 REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 99
RECTIFIER INPUT TERMINAL DETAIL PHASE A AC INPUT PHASE B TO UPS RECTIFIER PHASE C DESCRIPTION: POWER TERMINAL LOCATIONS DRAWING NO 164201586-6 22 of 34 REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 100
WITHOUT BIB PHASE C PHASE A AC OUTPUT PHASE B TO CRITICAL LOAD PHASE C DESCRIPTION: POWER TERMINAL LOCATIONS DRAWING NO 164201586-6 23 of 34 REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 101
TO BYPASS PHASE C PHASE A AC OUTPUT TO CRITICAL PHASE B LOAD PHASE C DESCRIPTION: POWER TERMINAL LOCATIONS DRAWING NO 164201586-6 24 of 34 REVISION: DATE: 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 102
PHASE B RECTIFIER PHASE C PHASE A AC OUTPUT PHASE B TO CRITICAL LOAD PHASE C DESCRIPTION: POWER TERMINAL LOCATIONS DRAWING NO 164201586-6 25 of 34 REVISION: DATE: 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 103
TO CRITICAL LOAD PHASE C PHASE A AC INPUT TO PHASE B RECTIFIER PHASE C DESCRIPTION: POWER TERMINAL LOCATIONS DRAWING NO 164201586-6 26 of 34 REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 104
TO BYPASS PHASE C PHASE C AC OUTPUT PHASE B TO CRITICAL LOAD PHASE A DESCRIPTION: POWER TERMINAL LOCATIONS DRAWING NO 164201586-6 27 of 34 REVISION: DATE: 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 105
PHASE B RECTIFIER PHASE C PHASE A AC INPUT TO BYPASS PHASE B PHASE C DESCRIPTION: POWER TERMINAL LOCATIONS DRAWING NO 164201586-6 28 of 34 REVISION: DATE: 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 106
TERMINAL BLOCK MOB 2 PHASE A AC INPUT PHASE B FROM UPM 2 PHASE C DESCRIPTION: POWER TERMINAL LOCATIONS DRAWING NO 164201586-6 29 of 34 REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 107
SLB OUTPUT TERMINAL DETAIL PHASE A AC OUTPUT PHASE B TO CRITICAL LOAD PHASE C DESCRIPTION: POWER TERMINAL LOCATIONS DRAWING NO 164201586-6 30 of 34 REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 108
PHASE C MOB 2 PHASE C AC INPUT PHASE B FROM UPM 2 PHASE A DESCRIPTION: POWER TERMINAL LOCATIONS DRAWING NO 164201586-6 31 of 34 REVISION: DATE: 092107 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 109
PHASE C MOB 2 PHASE C AC INPUT PHASE B FROM UPM 2 PHASE A DESCRIPTION: POWER TERMINAL LOCATIONS DRAWING NO 164201586-6 32 of 34 REVISION: DATE: 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 110
MOB 1 MOB 2 PHASE C AC INPUT PHASE B FROM UPM 2 PHASE A DESCRIPTION: POWER TERMINAL LOCATIONS DRAWING NO 164201586-6 33 of 34 REVISION: DATE: 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 111
SLB OUTPUT TERMINAL DETAIL PHASE A AC OUTPUT PHASE B TO CRITICAL LOAD PHASE C DESCRIPTION: POWER TERMINAL LOCATIONS DRAWING NO 164201586-6 34 of 34 REVISION: DATE: 062806 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 112
Contacts used for backup control (pull chain) for MOB 2 Aux 2 Contact Common parallel operation. INTERFACE AND CONTROL WIRING DESCRIPTION: INSTALLATION NOTES AND TERMINAL LOCATIONS DRAWING NO 164201586-7 1 of 4 REVISION: DATE: 063006 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 113
Use twisted pair wires for each alarm input and common. INTERFACE AND CONTROL WIRING DESCRIPTION: INSTALLATION NOTES AND TERMINAL LOCATIONS DRAWING NO 164201586-7 2 of 4 REVISION: DATE: 063006 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 114
1+1 PARALLEL REDUNDANT INTERFACE AND CONTROL WIRING DESCRIPTION: CONFIGURATION INSTALLATION NOTES AND TERMINAL LOCATIONS BACKUP CONTROL DRAWING NO 3 of 4 (PULL CHAIN) WIRING 164201586-7 REVISION: DATE: 063006 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 115
UPM 2 1+1 PARALLEL REDUNDANT INTERFACE AND CONTROL WIRING DESCRIPTION: CONFIGURATION INSTALLATION NOTES AND TERMINAL LOCATIONS MOB MONITORING WIRING DRAWING NO 4 of 4 164201586-7 REVISION: DATE: 063006 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 116
F F i i g g u u r r e e 8 8 4 4 . . 1 1 6 6 4 4 2 2 0 0 1 1 5 5 8 8 6 6 - - 8 8 U U P P S S S S i i d d e e c c a a r r D D i i m m e e n n s s i i o o n n s s ( ( S S h h e e e e t t 1 1 ) ) 40 kVA and 80 kVA UPS WITH SIDECAR DESCRIPTION: UPS SIDECAR DIMENSIONS DRAWING NO 164201586-8 1 of 4 REVISION: DATE: 092107 Dimensions are in millimeters [inches] EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
BOTTOM VIEW 40 KVA AND 80 KVA UPS DESCRIPTION: UPS SIDECAR DIMENSIONS WITH SIDECAR DRAWING NO 164201586-8 2 of 4 REVISION: DATE: 092107 Dimensions are in millimeters [inches] EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 118
F F i i g g u u r r e e 8 8 6 6 . . 1 1 6 6 4 4 2 2 0 0 1 1 5 5 8 8 6 6 - - 8 8 U U P P S S S S i i d d e e c c a a r r D D i i m m e e n n s s i i o o n n s s ( ( S S h h e e e e t t 3 3 ) ) 120 KVA AND 160 KVA UPS WITH SIDECAR DESCRIPTION: UPS SIDECAR DIMENSIONS DRAWING NO 164201586-8 3 of 4 REVISION: DATE: 031505 Dimensions are in millimeters [inches] EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 119
BOTTOM VIEW 120 KVA AND 160 KVA UPS DESCRIPTION: UPS SIDECAR DIMENSIONS WITH SIDECAR DRAWING NO 164201586-8 4 of 4 REVISION: DATE: 031505 Dimensions are in millimeters [inches] EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 120
F F i i g g u u r r e e 8 8 8 8 . . 1 1 6 6 4 4 2 2 0 0 1 1 5 5 8 8 6 6 - - 9 9 U U P P S S S S i i d d e e c c a a r r D D i i m m e e n n s s i i o o n n s s ( ( S S h h e e e e t t 1 1 ) ) L15 −20r−40kVA L21 −20r−40kVA L15 −20R L21 −20R DESCRIPTION: EXTERNAL POWER RECEPTACLE LOCATIONS DRAWING NO 1 of 9 164201586-9 REVISION: DATE: 082510 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 121
F F i i g g u u r r e e 8 8 9 9 . . 1 1 6 6 4 4 2 2 0 0 1 1 5 5 8 8 6 6 - - 9 9 U U P P S S S S i i d d e e c c a a r r D D i i m m e e n n s s i i o o n n s s ( ( S S h h e e e e t t 2 2 ) ) L15 −30r−40kVA L21 −30r−40kVA L15 −30R L21 −30R DESCRIPTION: EXTERNAL POWER RECEPTACLE LOCATIONS DRAWING NO 2 of 9 164201586-9 REVISION: DATE: 082510 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 122
F F i i g g u u r r e e 9 9 0 0 . . 1 1 6 6 4 4 2 2 0 0 1 1 5 5 8 8 6 6 - - 9 9 U U P P S S S S i i d d e e c c a a r r D D i i m m e e n n s s i i o o n n s s ( ( S S h h e e e e t t 3 3 ) ) L22 −20r− −30r−40kVA L22 −20R L22 −30R DESCRIPTION: EXTERNAL POWER RECEPTACLE LOCATIONS DRAWING NO 3 of 9 164201586-9 REVISION: DATE: 082510 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 123
C (L3) C (L3) A (L1) B (L2) C (L3) L6 −20r−40kVA L6 −30r−40kVA DESCRIPTION: EXTERNAL POWER RECEPTACLE LOCATIONS DRAWING NO 4 of 9 164201586-9 REVISION: DATE: 082510 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 124
F F i i g g u u r r e e 9 9 2 2 . . 1 1 6 6 4 4 2 2 0 0 1 1 5 5 8 8 6 6 - - 9 9 U U P P S S S S i i d d e e c c a a r r D D i i m m e e n n s s i i o o n n s s ( ( S S h h e e e e t t 5 5 ) ) iec400 −40 iec208 −40 DESCRIPTION: EXTERNAL POWER RECEPTACLE LOCATIONS DRAWING NO 5 of 9 164201586-9 REVISION: DATE: 082510 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 125
F F i i g g u u r r e e 9 9 3 3 . . 1 1 6 6 4 4 2 2 0 0 1 1 5 5 8 8 6 6 - - 9 9 U U P P S S S S i i d d e e c c a a r r D D i i m m e e n n s s i i o o n n s s ( ( S S h h e e e e t t 6 6 ) ) L15 −30r− −30r−80kVA L15 −30R L21 −30R DESCRIPTION: EXTERNAL POWER RECEPTACLE LOCATIONS DRAWING NO 6 of 9 164201586-9 REVISION: DATE: 082510 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 126
F F i i g g u u r r e e 9 9 4 4 . . 1 1 6 6 4 4 2 2 0 0 1 1 5 5 8 8 6 6 - - 9 9 U U P P S S S S i i d d e e c c a a r r D D i i m m e e n n s s i i o o n n s s ( ( S S h h e e e e t t 7 7 ) ) L22 −20r−80kVA L22 −30r−80kVA L22 −20R L22 −30R L22 −30r−120kVA L22 −30R DESCRIPTION: EXTERNAL POWER RECEPTACLE LOCATIONS DRAWING NO 7 of 9 164201586-9 REVISION: DATE: 082510 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 127
F F i i g g u u r r e e 9 9 5 5 . . 1 1 6 6 4 4 2 2 0 0 1 1 5 5 8 8 6 6 - - 9 9 U U P P S S S S i i d d e e c c a a r r D D i i m m e e n n s s i i o o n n s s ( ( S S h h e e e e t t 8 8 ) ) iec208 −80 iec400 −120 DESCRIPTION: EXTERNAL POWER RECEPTACLE LOCATIONS DRAWING NO 8 of 9 164201586-9 REVISION: DATE: 082510 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 128
F F i i g g u u r r e e 9 9 6 6 . . 1 1 6 6 4 4 2 2 0 0 1 1 5 5 8 8 6 6 - - 9 9 U U P P S S S S i i d d e e c c a a r r D D i i m m e e n n s s i i o o n n s s ( ( S S h h e e e e t t 9 9 ) ) iec400 − −160 DESCRIPTION: EXTERNAL POWER RECEPTACLE LOCATIONS DRAWING NO 9 of 9 164201586-9 REVISION: DATE: 082510 EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Page 129
Installation Information EATON® 9390 UPS (40–80 kVA) Sidecar Installation and Operation Manual 164201586—Rev G...
Need help?
Do you have a question about the 9390 and is the answer not in the manual?