6.2 System Power-On

Power on batteries within 24 hours after unpacking. If the batteries cannot be
powered on in time, put them in the original packaging and place them in a dry
indoor environment without corrosive gases. During later maintenance, ensure
that the power-off time does not exceed 24 hours. Otherwise, the equipment may
be damaged.
Power-On Process
Step 1 Turn on the ESS switch.
Step 2 At the AC switch between the inverter and the power grid, use a multimeter to
measure the grid voltage and ensure that the voltage is within the allowed
operating voltage range of the inverter. If the voltage is not in the allowed range,
check the circuits.
Step 3 Turn on the AC switch between the inverter and the power grid.
Step 4 Turn on the DC switch (if any) between the PV strings and the inverter.
Step 5 (Optional) Remove the knob locking screw next to the DC switch on the inverter.
Step 6 Set the DC switch on the inverter to ON.
Issue 01 (2024-03-27)
Check Item
Cable routing
Cable binding
Reliable grounding
Switch status
Cable connection
Unused terminal and port
Installation environment
CA UTION
Copyright © Huawei Digital Power Technologies Co., Ltd.
6 Power-On and Commissioning
Expected Result
Cables are routed properly as required
by the customer.
Cable ties are evenly distributed and no
sharp edge exists.
The PE cable is connected correctly,
securely, and reliably.
The DC SWITCH and all switches
connected to the ESS are OFF.
DC input power cables, ESS cables, and
signal cables are connected correctly
and securely.
Unused terminals and ports are
covered by watertight caps.
The installation space is proper, and
the installation environment is clean
and tidy.
68