UFM-H2O Series
Ultrasonic Flow Meter
Installation Instructions
When installing the meter, the upstream straight pipe line should be
pump (D is the pipe diameter), and ensure full pipe.
1
{
Cut 62.8mm of pipe
3
Install water meter with 3 screws to fix the flange
averagely, then spot welding.
Correct Install Position
Correct Installation Point
DN80
5D
3D
Lowest Point of the Pipe Line, Full Pipe.
Upstream Straight Pipe Line >= 5 Pipe Diameters
(Battery Operated)
water meter thickness 50.8mm
2pcs seal gasket thickness 6mm
5D, downstream straight pipe line should be
2
Install Companion Flange
4
Flow Direction
Install with seal gasket, and tighten bolts.
Make sure the direction arrow on water meter is
as the same as the direction of flow.
Wrong Installation Point
Highest Point of the Pipe Line, Pipe would not be Full.
Upstream Straight Pipe Line >= 3 Pipe Diameters
www.iconprocon.com | sales@iconprocon.com | 905.469.9283